Corby Cube

{{Short description|Municipal building in Corby, Northamptonshire, England}}

{{Use dmy dates|date=April 2022}}

{{Use British English|date=April 2022}}

{{Infobox building

| name = Corby Cube

| native_name =

| former_names =

| alternate_names =

| image = Corby Cube.jpg

| caption = Corby Cube building 2012

| map_type = Northamptonshire

| map_dot_label = Corby Cube

| location = Corby, Northamptonshire

| address =

| coordinates = {{coord|52.48723|N|0.70446|W|type:landmark_region:GB|display=inline,title}}

| inauguration_date = 2010

| architect = Hawkins\Brown

| main_contractor = Galliford Try

| renovation_date =

| ren_firm =

| owner = North Northamptonshire Council

}}

Corby Cube is a municipal building in the town of Corby, Northamptonshire, England. Built in 2010, it is occupied by North Northamptonshire Council as its headquarters, but was originally built for Corby Borough Council (abolished in 2021). The building houses a council chamber, a register office, a public library, a 400-seat theatre and a 100-seat multi-use studio space.

History

The building with was designed by Hawkins\Brown and built by Galliford Try at a cost of £47.5 million,{{cite web|url=https://www.constructionmanagermagazine.com/news/review-reveals-corby-cube-tale-woe/|title=Review reveals Corby Cube tale of woe|date=19 July 2012|publisher=Construction Manager Magazine|accessdate=21 April 2020}} opened as the headquarters of Corby Borough Council on 2 November 2010.

Financial and building controversies

A report by Corby Borough Council in 2012 revealed that the Cube was built with dangerous design flaws and almost double its original estimated costs and a capacity of only half of what was planned.{{cite news |title=Corby Cube built to 'dangerous' design, report says |url=https://www.bbc.co.uk/news/uk-england-northamptonshire-17852709 |location = London |work=BBC News |date=26 April 2012|accessdate=15 November 2020}}{{cite news |title=Corby councillors 'lost control' of Cube project |url=https://www.bbc.co.uk/news/uk-england-northamptonshire-17663690 |location = London |work=BBC Online News |date=10 April 2012|accessdate=15 November 2020}} In 2012 the working group of the council’s Overview and Scrutiny Panel published its report into Cube. It looks into the development and construction of the building. However, the full report contained commercial, financial and legally sensitive information so the public version of the report which was issued was heavily redacted with considerable blanking of text.{{cite web |url=http://www.corby.gov.uk/sites/default/files/documents/files/Public%20Report%20of%20Scrutiny%20Review%2C%20The%20Cube%2C%20Parkland%20Gateway%2C%20July%202012_0.pdf |title=PUBLIC REPORT of SCRUTINY REVIEW into THE CUBE, PARKLANDS GATEWAY Volume 1 (Public Version) |author=Corby Borough Council |date= March 2010|publisher=CBC |access-date=12 August 2012}}

In August 2012, the firm of architects of the Cube, Hawkins\Brown,{{cite web|url=http://www.hawkinsbrown.com/|title=Home - Hawkins\Brown|work=hawkinsbrown.com|accessdate=15 November 2020}} threatened to take Corby council to court over the report into the £12 million authority-overspend on the Cube complex. Along with criticising the council board that ran the building project, the report claims architects Hawkins\Brown did not stick to its brief.{{cite news|title=Legal action threat by architects over Corby Cube report|url=https://www.bbc.co.uk/news/uk-england-northamptonshire-19182015|location = London|work = BBC News|date=9 August 2012|access-date=15 November 2020}} Among its conclusions, the report stated that the current Labour-controlled council: "incurred substantial unforeseen costs in order to bring the building into an occupiable state but with limitations on occupancy still unresolved". In September 2012, Hawkins\Brown withdrew its threat of legal action against the borough council. The firm had, however, written to every borough councillor, asking for a chance to defend itself. Councillors were told not to respond "for legal reasons".{{cite news|title=Corby Cube overspend: Architects withdraw legal action threat|url=https://www.bbc.co.uk/news/uk-england-northamptonshire-19464638|location = London|work = BBC Online News|date=3 September 2012|accessdate=15 November 2020}}

In February 2013, water began dripping through the council chamber's ceiling forcing councillors to hold meetings in the canteen. This followed snow and heavy rain. The BBC reported that the Cube cost £47 million, over budget by £12 million, but the final report on the project had not yet been released.{{cite news|url=https://www.bbc.co.uk/news/uk-england-northamptonshire-21429815|title=BBC News - Corby Cube flood: Councillors hold meetings in canteen|work=BBC News|date=12 February 2013 |access-date=9 February 2015}} Also in February, the length of time taken to publish the audit report into the overspend was called "very disappointing" by Local Government Secretary of State Eric Pickles.{{cite news|url=https://www.bbc.co.uk/news/uk-england-northamptonshire-21547640|title=BBC News - Audit report into Corby Cube delay concern|work=BBC News|date=22 February 2013 |access-date=9 February 2015}}

In June 2013 auditors found that the council had sold land now being developed by Tesco for millions of pounds below its market value. Corby Borough Council "may have made decisions contrary to law" in its management of a £67 million regeneration scheme, auditors KPMG said.{{cite news| url = https://www.bbc.co.uk/news/uk-england-northamptonshire-22953515|title = Corby Council's regeneration schemes 'may have broken law'| work = BBC News| access-date = 18 June 2012}} Also in June 2013, management of regeneration programmes, including the Cube, by Corby Council was condemned by consultants appointed by the Audit Commission. KPMG said arrangements obscured who should make key decisions, oversight at critical points was insufficient and project and financial management was poor.{{cite news| url = https://www.bbc.co.uk/news/uk-england-northamptonshire-22989439| title = Corby regeneration projects management condemned| work = BBC News| access-date = 27 July 2012}}

In July 2013 the Conservative group on Corby Council handed what they described as "suspicious" findings of an audit report into the financial dealings of Corby Borough Council to the police for investigation.{{cite news| url = https://www.bbc.co.uk/news/uk-england-northamptonshire-23477085

| title = Corby Cube: Police given 'suspicious' council report| work = BBC News| access-date = 27 July 2012}} In August 2013 it was announced than another £600,000 was needed to mend roofs that have been leaking since the building was occupied. Work also needs completing on office space in the building which does not meet building fire safety regulations.{{Citation

| url = https://www.bbc.co.uk/news/uk-england-northamptonshire-23841179

| title = Corby Cube: Extra £600k needed

| work = BBC News website

| date = 26 August 2013

| publisher = BBC

| access-date = 27 August 2013

}}

Chief Executive Norman Stronach later said that the council would "seek redress" from the architect and contractor and that action to recover extra money spent on the Cube is "a growing inevitability".{{Citation

| url = https://www.bbc.co.uk/news/uk-england-northamptonshire-23854192

| title = Corby Cube legal action 'a growing inevitability'

| work = BBC News website

| date = 28 August 2013

| publisher = BBC

| access-date = 28 August 2013

}}

On 8 December 2014, Northamptonshire Police began an investigation into financial dealings by Corby Borough Council. In July 2013, Conservative councillors had handed the "suspicious" findings of an audit report to the police to see if a crime had been committed. The audit report examined four major projects, including the Corby Cube, the cost of which went from £35 million to £47 million.{{cite news|url=https://www.bbc.co.uk/news/uk-england-northamptonshire-30376836|title=BBC News - Corby council's 'financial dealings subject to police probe'|work=BBC News|date=8 December 2014 |access-date=9 February 2015}}

In January 2015, the BBC reported that repairs to the Cube were still going on five years after it opened.{{Citation

| url= https://www.bbc.co.uk/news/uk-england-northamptonshire-30574379

| title = Corby Cube repairs ongoing five years after it opened

| work = BBC News website

| date = 3 January 2015

| publisher = BBC

| access-date = 3 January 2015

}}

In March 2015 whistle-blower Steven Redfern, Corby Borough Council's former head of property, lodged a £1 million damages claim at the High Court against Corby Council. Redfern said he became "a target for people's venom" after complaining about high-profile land deals in the town.{{Citation

| url= https://www.bbc.co.uk/news/uk-england-northamptonshire-31698003

| title = Whistle-blower sues Corby Council for £1m

| work = BBC News website

| date = 4 March 2015

| publisher = BBC

| access-date = 4 March 2015

}} The case was listed to go to the High Court in the summer, but was settled out of court for an undisclosed sum.{{Citation

| url=https://www.bbc.co.uk/news/uk-england-northamptonshire-31767739

| title ='Bullied' whistle-blower settles £1m claim out of court

| work = BBC News website

| date =7 March 2015

| publisher = BBC

| access-date = 7 March 2015

}}

In October 2015, Corby Council stated that work on the Corby Cube had been completed, five years after it opened but with a £13 million overspend.{{Citation

| url = https://www.bbc.co.uk/news/live/uk-england-northamptonshire-34404452

|title = Updates for Tuesday 6 October 2015

|date = 6 October 2015

| publisher = BBC

| access-date = 6 October 2015

}}

On 3 February 2020, the Council was advised to abandon any legal action against the builder and designer.{{cite web|url=https://www.northantstelegraph.co.uk/news/politics/council/corby-cube-legal-action-set-be-dropped-its-impossible-attribute-blame-failings-1382961|title=Corby Cube legal action set to be dropped as it's 'impossible to attribute blame' for failings|date=3 February 2020|publisher=Northants Telegraph|accessdate=21 April 2020}}