MicroPlanner X-Pert
{{Use mdy dates|date=September 2012}}
{{Infobox software
| name = Micro Planner X-Pert
| developer = Micro Planning International
| latest_release_version = 3.5
| latest_release_date = November 19, 2007
| operating_system = Microsoft Windows
| genre = Project management software
| license = EULA
| website =[http://www.microplanning.com/ Micro Planning International Website]
}}
Micro Planner X-Pert (or X-Pert) is a project management software package in continuous development since 1979.
Overview
X-Pert is geared to producing critical path method and PERT schedules for major, long-term projects (in one case[http://www.mosaicprojects.com.au/Resources_Papers_012.html VIPER] a duration now approaching 40 years).
Developed by users and contributors to the ICL 1900 PERT mainframe package, X-Pert is one of the few packages still fully supporting the activity on arrow project network process.
X-Pert supports the full cycle of project management – through multi-level work breakdown structure creation, transition to multiple projects using critical path diagrams and Gantt chart presentation.
X-Pert is available as Software as a Service (SaaS) running in the cloud, for a low monthly subscription
History
At its first commercial release in 1980,[http://www.mosaicprojects.com.au/Company_People_MPI.html#Software Mosaic Project Services – Company History] Micro Planner was the first project management package for a micro computer.
First developed for the Apple II computer in 1979, versions have also existed at various times for the Apple ///, Sirius Systems Technology Victor, Macintosh, Silicon Graphics IRIX platforms, and currently for Microsoft Windows.
With the simultaneous release of Version 6 in 1988, for both Macintosh and Windows; Micro Planner became the first cross-platform project management solution for companies with a mixed hardware environment.
As of 2014 a 32-bit version for Windows and Mac OS X is under advanced development.
Specifications
class="wikitable" | |
Max. No Operations per project: | 15,000 |
Max. No Subprojects per project: | 100 |
Max. No Operations per sub-project: | 1,364 |
Max. No Resources: | 500 per project 20 per operation |
Max. No Work Breakdown Elements: | 1,500 |
Max. No Calendars per project: | 500 |
Flexible Time Units: | Weeks, Days, Shifts, Hours, Minutes |
Number of Zones: | Zone Label (16 character) 500 |
Number of Responsibilities Label (16 character): | 500 |
Number of Cost Label (16 character): | 500 |
Sort Code (8 character): | Full positional select / sort |
Link Types: | Finish-to-Start, Start-to-Start, Finish-to-Finish & Start-to-Finish |
Import/Export file formats: | TEXT, DIF, CSV, XML & MPX (Import only) |
See also
References
{{reflist|2}}
External links
- [http://www.microplanning.com/ Micro Planning International Website]
- [http://www.microplanning.co.uk/ Micro Planning UK Website]
- [http://www.microplanning.com.au/ Micro Planning International Asia Pacific Website]
Category:Project management software
Category:Critical Path Scheduling
{{business-software-stub}}