Project Aqua

{{Short description|Proposed hydroelectric scheme for Waitaki River, New Zealand}}

{{Use dmy dates|date=April 2025}}

{{Use New Zealand English|date=August 2014}}

Project Aqua was a hydroelectric scheme proposed for the lower Waitaki River in New Zealand.[http://www.scoop.co.nz/stories/BU0307/S00023.htm The Project Aqua Design Difference], Wednesday, 2 July 2003, Press Release: Meridian Energy Although the scheme had considerable support from some locals, it met with opposition from many other groups, and Meridian Energy decided in March 2004 not to go ahead with the project.

The plan

The plan was to divert river water at the rate of up to 280 cubic metres per second into a separate canal for six power stations. This was on top of the three dams already in the upper Waitaki River. The scheme would have produced approximately 520MW of power – enough to supply a city the size of Christchurch.

Objections

The objections to the scheme included land issues, the disruption during construction, and concerns about the sustainability of the river.{{cite news|last1=Cumming|first1=Geoff|title=Who killed Project Aqua?|url=https://www.nzherald.co.nz/nz/who-killed-project-aqua/2ZZS7RTC5IF6MVYCPLVJHR4FCI/|accessdate=24 August 2024|work=The New Zealand Herald|date=3 April 2004}} Meridian Energy was working on a large scale mitigation process, whereby issues could be identified and mitigated, when the scheme was finally cancelled.

Abandonment and impact

On 29 March 2004, Meridian announced that they would not continue with Project Aqua. Among their reasons were the uncertainty in gaining access to the water, that Aqua could not come on line soon enough to meet New Zealand's growing electricity demand, the amount of money it was costing the company, design changes due to geology reports, and the Resource Management Act making it difficult to get consent for large water based projects.{{cite news |url=http://www.nzherald.co.nz/business/news/article.cfm?c_id=3&objectid=3558845 |title=Speed up RMA, says business |author=Oliver, Paula |date=5 April 2004 |work=The New Zealand Herald |accessdate=4 November 2011}}

Meridian's 2004 annual report states that they lost NZ$38.7 million on the project. At the time of cancellation they had spent considerably more than this, but much of the expenditure was for assets such as land that they would later sell.

Possible alternative scheme

Subsequently, Meridian proceeded to develop an alternative hydroelectric scheme along the same stretch of the Waitaki River – the North Bank tunnel project. They received water uses consents from Environment Canterbury in December 2008 but work on the project was suspended in January 2013.{{cite news|url=http://www.nzherald.co.nz/business/news/article.cfm?c_id=3&objectid=10673853|title=Faultlines spark redesign in Waitaki power project|work=The New Zealand Herald|date=16 September 2010}}{{cite news| url=http://www.oamarumail.co.nz/news/meridian-suspends-land-negotiations/1723832/| title=Meridian suspends land negotiations| date=20 January 2013| first=Jacquie |last=Webby| work=Oamaru Mail| archiveurl=https://web.archive.org/web/20130212130003/http://www.oamarumail.co.nz/news/meridian-suspends-land-negotiations/1723832/ | archivedate=12 February 2013}}

References

{{Reflist}}