Crawler-transporter

{{short description|NASA rocket transport vehicle}}

{{Use American English|date=January 2014}}

{{Infobox automobile

| name = Crawler-transporter

| image = Crawler-Transporter.jpg

| image_size = 275px

| caption =

| aka = Missile Crawler Transporter Facilities

| manufacturer = Marion Power Shovel Company

| model_years = 1965

| engine = {{ubli

| 2 × {{convert|2750|hp|kW|abbr=on|lk=on|order=flip}} V16 ALCO 251C diesel engines, driving 4 × {{convert|1341|hp|kW|abbr=on|order=flip}} generators for traction

| 2 × {{convert|1065|hp|kW|abbr=on|order=flip}} engines driving 2 × {{convert|1006|hp|kW|abbr=on|order=flip}} generators powering auxiliaries: jacking, steering, lighting, and ventilating.

}}

| transmission = 16 × traction motors, 4 per corner

| length = {{convert|131|ft|m|0|abbr=on|order=flip}}

| width = {{convert|114|ft|m|0|abbr=on|order=flip}}

| height = Adjustable, {{convert|20|to|26|ft|m|0|abbr=on|order=flip}}

| weight = {{convert|2721|tonne|lb|abbr=on|sigfig=3}}

| sp = us

| module =

{{Infobox NRHP

| embed = yes

| name = Missile Crawler Transporter Facilities

| nrhp_type = nrhp

| location = Kennedy Space Center, Florida

| added = January 21, 2000

| refnum = 99001643

| mpsub = John F. Kennedy Space Center MPS

}}

}}

The crawler-transporters, formally known as the Missile Crawler Transporter Facilities, are a pair of tracked vehicles used to transport launch vehicles from NASA's Vehicle Assembly Building (VAB) along the Crawlerway to Launch Complex 39. They were originally used to transport the Saturn IB and Saturn V rockets during the Apollo, Skylab and Apollo–Soyuz programs. They were then used to transport Space Shuttles from 1981 to 2011. The crawler-transporters carry vehicles on the mobile launcher platforms (MLPs) used by NASA, and after each launch return to the pad to take the platform back to the VAB.

The two crawler-transporters were designed and built by Marion Power Shovel Company using some components designed and built by Rockwell International at a cost of {{USD|14 million}} ({{USD|128.5 million}} in 2022) each. Upon its construction, the crawler-transporter became the largest self-powered land vehicle in the world until it was beaten in 2013 with the production of the ultraheavy XGC88000 crawler crane. While other vehicles such as bucket-wheel excavators like Bagger 288, dragline excavators like Big Muskie and power shovels like The Captain are significantly larger, they are powered by external sources.

The two crawler-transporters were added to the National Register of Historic Places on January 21, 2000.

Specifications

File:Crawler-transporter cutaway view.gif

The crawler-transporter has a mass of {{convert|2721|tonne|e6lb ST|0|abbr=off}} and has eight tracks, two on each corner. Each track has 57 shoes, and each shoe weighs {{convert|1984|lb|kg|abbr=on|order=flip}}. The vehicle measures {{convert|131|by|114|ft|m|order=flip|sp=us}}. The height from ground level to the platform is adjustable from {{convert|20|to|26|ft|m|abbr=on|order=flip}}, and each side can be raised and lowered independently of the other. The crawler uses a laser guidance system and a leveling system to keep the Mobile Launcher Platform level within 10 minutes of arc (0.16 degrees; about {{convert|1|ft|cm|abbr=on|order=flip}} at the top of the Saturn V), while moving up the 5 percent grade to the launch site. A separate laser docking system provides pinpoint accuracy when the crawler-transporter and Mobile Launch Platform are positioned in the VAB or at the launch pad. A team of nearly 30 engineers, technicians and drivers operate the vehicle, centered on an internal control room, and the crawler is driven from two control cabs located at either end. Before the launch the crawler-transporter is removed.

The crawlers were overhauled in 2003 with upgrades to the Motor Control Center, which houses the switchgear and electrical controls of all of major systems on board; a new engine and pump ventilation system; new diesel engine radiators; and replacement of the two driver cabs on each vehicle (one on each end). After the 2003 refit, each crawler had 16 traction motors, powered by four {{convert|1341|hp|kW|abbr=on|order=flip}} generators, in turn driven by two {{convert|2750|hp|kW|abbr=on|order=flip}} V16 ALCO 251C diesel engines. Two {{convert|1006|hp|kW|abbr=on|order=flip}} generators, driven by two {{convert|1065|hp|kW|abbr=on|order=flip}} engines, were used for jacking, steering, lighting, and ventilating. Two {{convert|201|hp|kW|abbr=on|order=flip}} generators were also available to power the Mobile Launcher Platform. The crawler's tanks held {{convert|5000|USgal|L|sp=us|order=flip}} of diesel fuel, and it burned {{convert|125.7|USgal/mi|L/km|sp=us|order=flip}}.

Due to their age and the need to support the heavier Space Launch System and its launch tower, in 2012–2014 the crawlers were undergoing an upgrade involving "new engines, new exhausts, new brakes, new hydraulics, new computers"; CT-2 was further upgraded in 2014–2016 to increase its lifting capacity from {{convert|12|to|18|e6lb|t|abbr=off|order=flip}}.

The crawlers traveled along the {{convert|5535|and|6828|m|km mi|1|abbr=on|order=out}} Crawlerways, to LC-39A and LC-39B, respectively, at a maximum speed of {{convert|1|mph|km/h|order=flip|sp=us}} loaded, or {{convert|2|mph|km/h|order=flip|abbr=on}} unloaded. The average trip time from the VAB along the Crawlerway to Launch Complex 39 is about five hours. Each Crawlerway is {{Convert|7|ft|m|0|abbr=on|order=flip}} deep and covered with Alabama and Tennessee river rock for its low friction properties to reduce the possibility of sparks. In 2000, NASA unearthed and restored an Apollo-era segment of the Crawlerway to provide access to High Bay 2 in the VAB in order to provide protection from a hurricane for up to three Shuttles at the same time.

Kennedy Space Center has been using the same two crawlers since their initial delivery in 1965. They are now nicknamed "Hans and Franz", after the parodic Austrian body-builder characters on Saturday Night Live, played by Dana Carvey and Kevin Nealon. In their lifetime, they have traveled more than {{convert|3400|mi|km|abbr=on|order=flip}}, about the same driving distance as from Miami to Seattle.

Future use

=Crawler-Transporter 2=

NASA currently uses crawler-transporter 2 to transport the Space Launch System with the Orion spacecraft atop it from the Vehicle Assembly Building to Launch Pad 39B for the Artemis missions. Early in 2016, NASA finished upgrading crawler-transporter 2 (CT-2) to a "Super Crawler" for use in the Artemis program. NASA performed a rollout of the Artemis 1 Space Launch System and Orion on March 17, 2022 for the first Wet Dress Rehearsal, and the rollout for launch, which launched in November 2022. The rollout for the WDR, marked the first time one of the crawler transporters rolled a launch vehicle to the launch pad since STS-135.

=Crawler-Transporter 1=

NASA had originally planned for crawler-transporter 1 to be used by commercial launch vehicles. In April 2016, then Orbital ATK, now Northrop Grumman Innovation Systems, and NASA entered negotiations for the lease of CT-1 and one of the four Vehicle Assembly Building bays. Northrop Grumman planned to use CT-1 to transport their OmegA from the Vehicle Assembly Building to Launch Pad 39B. OmegA was cancelled in September of 2020 after Northrop Grumman lost the National Security Space Launch contract to United Launch Alliance and SpaceX.

Gallery

File:LC-39 Observation gantry pano.jpg|Crawlerway junction at the LC-39 observation gantry. The right track leads to pad LC-39A (pictured with {{OV|Endeavour}}), while the left track leads to pad LC-39B.

File:Ap11-KSC-69PC-241HR.jpg|Saturn V, service structure and MLP on top of a crawler

File:Crawlertreds.jpg|Detail of crawler treads

File:STS-79 rollout.jpg|{{OV|Atlantis}} (STS-79) atop an MLP (and crawler beneath)

File:STS-114 rollout.jpg|A crawler-transporter carrying {{OV|Discovery|full=no}} (STS-114) travels the ramp to Launch Pad 39B. The vehicle's back end can be raised, keeping the Shuttle and the MLP level.

File:STS-51-L - Space Shuttle Challenger on the Crawler-Transporter.jpg|{{OV|Challenger}} atop an MLP atop a crawler, in transit to its launch pad prior to its final flight, January 28, 1986

File:Ares I-X rollout on mobile launch platform.jpg|Crawler carrying the Ares I-X atop an MLP

See also

References

{{Reflist|refs=

{{Cite news |url=https://www.bbc.com/future/article/20190626-apollo-in-50-numbers-the-rocket |title=Apollo in 50 numbers: The rocket |publisher=BBC |last=Hollingham |first=Richard |date=June 26, 2019 |access-date=June 27, 2019 |archive-url=https://web.archive.org/web/20220317071533/https://www.bbc.com/future/article/20190626-apollo-in-50-numbers-the-rocket |archive-date=2022-03-17 |url-status=live }}

{{cite news |url=https://www.nasaspaceflight.com/2016/02/ct-2-completes-super-crawler-modifications-sls/ |title=CT-2 completes Super Crawler modifications for SLS program |work=NASA Spaceflight |first1=Chris |last1=Gebhardt |first2=Chris |last2=Bergin |date=February 23, 2016 |access-date=June 24, 2016 |archive-url=https://web.archive.org/web/20160430040515/https://www.nasaspaceflight.com/2016/02/ct-2-completes-super-crawler-modifications-sls/ |archive-date=April 30, 2016 |url-status=live }}

{{cite web |url=http://dsc.discovery.com/fansites/dirtyjobs/episode/episode-tab-04.html |title=The Complete Dirty Jobs Show Guide: 2007 |work=Discovery.com |archive-url=https://web.archive.org/web/20121012074054/http://dsc.discovery.com/fansites/dirtyjobs/episode/episode-tab-04.html |archive-date=October 12, 2012 |url-status=dead }}

{{cite magazine |url=https://www.motortrend.com/reviews/0705dp-nasa-diesel-shuttle-crawler/ |title=NASA Diesel-Powered Shuttle Hauler - The Crawlers |magazine=MotorTrend |first=Jason |last=Sands |date=May 17, 2007 |access-date=April 1, 2013 |archive-url=https://web.archive.org/web/20220313044846/https://www.motortrend.com/reviews/0705dp-nasa-diesel-shuttle-crawler/ |archive-date=March 13, 2022 |url-status=live }}

{{cite news |url=https://floridapolitics.com/archives/207644-orbital-atk-picked-use-nasas-vehicle-assembly-building-kennedy-space-center/ |title=Orbital ATK picked to use NASA's Vehicle Assembly Building at Kennedy Space Center |work=Florida Politics |first=Scott |last=Powers |date=April 21, 2016 |access-date=June 24, 2016 |archive-url=https://web.archive.org/web/20160803223152/http://floridapolitics.com/archives/207644-orbital-atk-picked-use-nasas-vehicle-assembly-building-kennedy-space-center |archive-date=August 3, 2016 |url-status=live}}

{{cite web |url=https://www.nasa.gov/mission_pages/constellation/main/Constellationfacilities.html |title=Kennedy Prepares to Host Constellation |publisher=NASA |date=September 28, 2007 |access-date=June 7, 2009 |archive-url=https://web.archive.org/web/20220314175158/https://www.nasa.gov/mission_pages/constellation/main/Constellationfacilities.html |archive-date=March 14, 2022 |url-status=live |last1=Siceloff |first1=Steven }}

{{cite web |url=http://mediaarchive.ksc.nasa.gov/detail.cfm?mediaid=26125 |title=KSC-05PD-1322 |publisher=NASA |date=June 15, 2005 |access-date=June 18, 2007 |archive-url=https://web.archive.org/web/20080109035956/http://mediaarchive.ksc.nasa.gov/detail.cfm?mediaid=26125 |archive-date=January 9, 2008 |url-status=dead}}

{{cite web |url=http://www-pao.ksc.nasa.gov/nasafact/count3teaf.htm |title=Countdown! NASA Launch Vehicles and Facilities |publisher=NASA |id=PMS 018-B |date=October 1991 |access-date=June 18, 2007 |url-status=dead |archive-url=https://web.archive.org/web/20080109045657/http://www-pao.ksc.nasa.gov/nasafact/count3teaf.htm |archive-date=January 9, 2008}}

{{cite news |url=https://www.nasa.gov/content/nasas-giant-crawlers-turn-50-years-old-pivot-toward-future-exploration |title=NASA's Giant Crawlers turn 50 Years Old, Pivot Toward Future Exploration |publisher=NASA |first=Linda |last=Herridge |date=February 22, 2015 |access-date=June 24, 2016 |archive-url=https://web.archive.org/web/20160620110128/http://www.nasa.gov/content/nasas-giant-crawlers-turn-50-years-old-pivot-toward-future-exploration/ |archive-date=June 20, 2016 |url-status=live }}

{{cite web |url=https://science.ksc.nasa.gov/facilities/crawlerway.html |title=Crawlerway to the Pad |publisher=NASA |date=October 6, 1993 |access-date=July 16, 2019 |archive-url=https://web.archive.org/web/20220106145248/https://science.ksc.nasa.gov/facilities/crawlerway.html |archive-date=January 6, 2022 |url-status=dead }}

{{cite web |url=https://science.ksc.nasa.gov/facilities/crawler.html |title=Crawler-Transporter |publisher=NASA |date=April 21, 2003 |access-date=June 18, 2020 |archive-url=https://web.archive.org/web/20200601012639/https://science.ksc.nasa.gov/facilities/crawler.html |archive-date=June 1, 2020 |url-status=dead}}

{{NRHP Focus|99001643}}

{{cite news |last1=Bergin |first1=Chris |title=All hail the Super Crawler – CT-2 put through its paces ahead of SLS |url=https://www.nasaspaceflight.com/2012/11/super-crawler-ct-2-through-paces-ahead-sls/ |work=NASASpaceflight.com |date=November 24, 2012 |archive-url=https://web.archive.org/web/20220418112733/https://www.nasaspaceflight.com/2012/11/super-crawler-ct-2-through-paces-ahead-sls/ |archive-date=April 18, 2022 |url-status=live }}

{{cite web |url=http://www.space.com/news/spaceshuttles/shuttle_safehaven_000812.html |title=Shuttle Safe Haven Opens at Kennedy Space Center |work=Space.com |last=Halvorson |first=Todd |date=August 13, 2000 |archive-url=https://web.archive.org/web/20050920102345/http://www.space.com/news/spaceshuttles/shuttle_safehaven_000812.html |archive-date=September 20, 2005 |url-status=dead }}

{{cite news|last=Wall|first=Mike|url=https://www.space.com/nasa-artemis-1-moon-mission-launch-may-2022 |title=NASA's Artemis 1 moon mission, 1st flight of new megarocket, won't launch until May |publisher=Space.com|date=25 February 2022|access-date=25 February 2022 |archive-url=https://web.archive.org/web/20220408221953/https://www.space.com/nasa-artemis-1-moon-mission-launch-may-2022 |archive-date=April 8, 2022 |url-status=live }}

{{cite news|last=Sandra|first=Erwin|url=https://spacenews.com/northrop-grumman-to-terminate-omega-rocket-program/|title=Northrop Grumman to terminate OmegA rocket program|publisher=SpaceNews|date=9 September 2020|access-date=11 February 2022}}

{{cite journal |url=http://sfa.nasa.gov/MISSIONPOSTERS/spotlight/spotlightCrawler.pdf |title=Crawler Transporter |journal=Return to Flight Spotlight |publisher=NASA |issue=1 |date=April 2004 |archive-url=https://web.archive.org/web/20090320065927/http://sfa.nasa.gov/MISSIONPOSTERS/spotlight/spotlightCrawler.pdf |archive-date=March 20, 2009 |url-status=dead }}

{{cite web |url=https://www.wnyc.org/story/284187-nasas-big-rig-and-we-mean-really-big-gets-a-tune-up-pics/ |title=NASA's Historic Giant Crawler Gets a Tune Up for Modern Times (Pics) |work=Transportation Nation |first=Matthew |last=Peddie |date=September 5, 2012 |url-status=live |archive-url=https://web.archive.org/web/20220418113531/https://www.wnyc.org/story/284187-nasas-big-rig-and-we-mean-really-big-gets-a-tune-up-pics/ |archive-date=April 18, 2022 }}

}}