Kigoma–Butare–Ngozi–Gitega High Voltage Power Line

{{Short description|High voltage power transmission line in Rwanda and Burundi}}

{{EngvarB|date=August 2022}}

{{Use dmy dates|date=August 2022}}

{{Infobox power transmission line

| name = Kigoma–Butare–Ngozi–Gitega High Voltage Power Line

| photo =

| caption =

| map =

| country = Rwanda and Burundi

| state =

| province =

| coordinates = {{coord|02|50|53|S|29|48|29|E|display=inline, title}}

| direction = North to South

| start = Kigoma, Rwanda

| through = Butare, Ngozi

| finish = Gitega, Burundi

| par =

| owner = Government of Burundi & Government of Rwanda

| partners = European Union & African Development Bank

| operator = REGIDESO Burundi & Rwanda Energy Group Limited

| cable_manufacturer =

| cable_installer =

| cable_layer =

| substation_manufacturer =

| substation_installer =

| contractors = Multiple

| construction = 2022

| expected = 2024

| construction_cost = €24.4 million

| est =

| decom =

| type =

| current_type = AC

| length = 140.7

| length_mi =

| tower_no =

| capacity =

| AC_voltage = 220kV

| DC_voltage =

| poles_no =

| circuits_no = 1

}}

The Kigoma–Butare–Ngozi–Gitega High Voltage Power Line, also Rwanda–Burundi High Voltage Power Line is a high voltage electricity power line, under construction, connecting the high voltage substation at Kigoma in Rwanda to another high voltage substation at Gitega in Burundi.{{cite web| work=Afrik21.africa | url=https://www.afrik21.africa/en/burundi-rwanda-a-power-line-will-interconnect-the-two-countries/ |title=Burundi/Rwanda: A power line will interconnect the two countries |date=1 August 2022 |author=Jean Marie Takouleu |access-date=1 August 2022 | location=Paris, France}}

Location

The 220 kilovolt power line starts at the Rwanda Energy Group (REG) 220kV substation in the town of Kigoma Rwanda, approximately {{convert|76.5|km|0}}, by road, southwest of Kigali, the capital and largest city of Rwanda.{{google maps| url=https://www.google.com/maps/dir/Kigali,+Rwanda/Kigoma,+Rwanda/@-2.0992742,29.9014067,10z/data=!3m1!4b1!4m14!4m13!1m5!1m1!1s0x19dca4258ed8e797:0xf32b36a5411d0bc8!2m2!1d30.0618851!2d-1.9440727!1m5!1m1!1s0x19c3481c7caec281:0x26691cc4c80407e2!2m2!1d29.7918194!2d-2.2581145!3e0 |title=Road Distance Between Kigali, Rwanda And Kigoma, Rwanda |access-date=2 August 2022}} From here, the power line travels to the southern Rwandan town of Butare (Huye), a road distance of about {{convert|51|km|0}}.{{google maps|

url=https://www.google.com/maps/dir/Kigoma,+Rwanda/Butare,+Rwanda/@-2.5514863,29.7128013,10z/data=!4m14!4m13!1m5!1m1!1s0x19c3481c7caec281:0x26691cc4c80407e2!2m2!1d29.7918194!2d-2.2581145!1m5!1m1!1s0x19c30e87584c8b97:0x71fbfafce20bdc47!2m2!1d29.7419201!2d-2.6005173!3e0 |title=Road Distance Between Kigoma, Rwanda And Butare, Rwanda |access-date=2 August 2022}} From Butare, the power line continues south to the international border with Burundi. It crosses the border and continues to the town of Ngozi, a road distance of approximately {{convert|75|km|0}}{{google maps| url=https://www.google.com/maps/dir/Butare,+Rwanda/Ngozi,+Burundi/@-2.7505783,29.7177768,9.75z/data=!4m14!4m13!1m5!1m1!1s0x19c30e87584c8b97:0x71fbfafce20bdc47!2m2!1d29.7419201!2d-2.6005173!1m5!1m1!1s0x19c395c892983515:0x6e532ed13010e115!2m2!1d29.8243599!2d-2.9107175!3e0 |title=Road Distance Between Butare, Rwanda And Ngozi, Burundi |access-date=2 August 2022}}

From Ngozi, power line travels in a general southerly direction to the city of Gitega, the capital of Burundi, a road distance of approximately {{convert|83|km|0}}, ending at another 220kV substation, this one owned by REGIDESO Burundi.{{google maps| url=https://www.google.com/maps/dir/Ngozi,+Burundi/Gitega,+Burundi/@-3.1694189,29.8677515,9z/data=!3m1!4b1!4m14!4m13!1m5!1m1!1s0x19c395c892983515:0x6e532ed13010e115!2m2!1d29.8243599!2d-2.9107175!1m5!1m1!1s0x19c14452ea1ca4e7:0x42aade0278ba3d8e!2m2!1d29.9246016!2d-3.4272755!3e0 |title=Road Distance Between Ngozi, Burundi And Gitega, Burundi |access-date=2 August 2022}} The length of this power line is reported to be {{convert|140.7|km|0}} from end to end, with {{convert|61.5|km|0}} in Rwanda and {{convert|79.2|km|0}} in Burundi.{{cite web| work=African Development Bank |title=Burundi-Rwanda Electricity Interconnection Project: Environmental And Social Impact Assessment (ESIA) Summary |

url=https://www.afdb.org/fileadmin/uploads/afdb/Documents/Environmental-and-Social-Assessments/Multinational_-_Projet_d%E2%80%99interconnexion_des_re%CC%81seaux_e%CC%81lectriques_Burundi_%E2%80%93_Rwanda_-_Summary_ESIA.pdf |date=August 2018 |author=African Development Bank |access-date=2 August 2022 | location=Abidjan, Ivory Coast}}

Overview

This power transmission line connects the electricity grid of Rwanda to that of neighboring Burundi. It is in line with the Nile Equatorial Lakes Subsidiary Action Program, Interconnection of Electric Grids Project, led by Regional Manager, Grania Rubomboras.{{cite web| work=ESI Africa |volume=2 of 2016 | url=http://www.spintelligentpublishing.com/Digital/ESI-Africa/issue2-2016/html5/index.html?page=80&noflash |title=Women In Energy: Leader Immersed In Power Projects |date=December 2016 |access-date=2 August 2022 |location=Cape Town, South Africa}} The power line is being developed to facilitate exchange of electricity between the two neighboring countries and to be ready to buy electricity from other countries in the Eastern Africa Power Pool (EAPP), who have surplus power to sell. The countries with surplus power in the EAPP include Ethiopia, Kenya and Uganda.{{cite web| url=https://www.theeastafrican.co.ke/tea/business/regional-high-voltage-lines-expected-by-2018--1340458 |title=Regional high voltage lines expected by 2018 |work=The EastAfrican | date=12 September 2015 |author=The EastAfrican |access-date=2 August 2022 |location=Nairobi, Kenya}}

Construction in Burundi

Construction in Burundi was launched in August 2020. The engineering, procurement and construction (EPC) contract was awarded to a consortium comprising Transrail Lighting from India and Hanbaek from South Korea. The Burundi portion of this power transmission line is funded by loans to the government of Burundi, provided by the African Development Bank and the European Union.

Construction in Rwanda

In 2018, it was reported that KfW was going to fund the Rwanda portion of this power line. In 2022, online media reported that the entire line in both countries would be funded by the African Development Bank and the European Union.

Other consideration

The power line is designed in a fashion that allows it to operate at either 110kV or 220kV, if and when the need arises. Work involves the construction of new substations at Kigoma and Gitega, as well as connecting both ends of the transmission power line to control centers in Kigali, Rwanda for the northern end and Bujumbura, Burundi for the southern end.