Gas
class="wikitable sortable"
! Name ! Operator ! Governorate ! Type ! Capacity (MW) ! Commission date ! Ref |
Beni Suef Power Plant
| UEEPC{{ref label|UEEPC|e}} | CCGT | 4,800 | 2018 |
Burullus Power Plant
| MDEPC{{ref label|MDEPC|c}} | CCGT | 4,800 | 2018 |
New Capital Power Plant
| CEPC {{ref label|CEPC|a}} | Cairo | CCGT | 4,800 | 2018 |
Cairo North Power Plant
| CEPC{{ref label|CEPC|a}} | Cairo | CCGT | 1,500 | Stage 1: 2004 Stage 2: 2007 |
Damietta Power Plant
| EDEPC{{ref label|EDEPC|b}} | Damietta | CCGT | 1,200 | 1989 |
El Atf Power Plant
| MDEPC{{ref label|MDEPC|c}} | CCGT | 750 | 2006 |
El Kureimat Power Plant
| UEEPC{{ref label|UEEPC|e}} | Minya | CCGT | 3,000 | Stage 1: 2008 Stage 2: 2010 |
El Nubaria Power Plant
| MDEPC{{ref label|MDEPC|c}} | CCGT | 2,250 | Stage 1: 2005 Stage 2: 2010 |
Hurghada Power Plant
| EDEPC{{ref label|EDEPC|b}} | Red Sea | CCGT | 143 | 2002 |
Sidi Krir Power Plant
| WDEPC{{ref label|WDEPC|d}} | CCGT | 750 | 2000 |
Talkha Power Plant
| MDEPC{{ref label|MDEPC|c}} | Dakahlia | CCGT | 290 | 1979 |
New Talkha Power Plant
| MDEPC{{ref label|MDEPC|c}} | Dakahlia | CCGT | 750 | 2007 |
{{note|CEPC}}Cairo Electricity Production Company
{{note|EDEPC}}East Delta Electricity Production Company
{{note|MDEPC}}Middle Delta Electricity Production Company
{{note|WDEPC}}West Delta Electricity Production Company
{{note|UEEPC}}Upper Egypt Electricity Production Company
Hydroelectric
class="wikitable sortable"
! Name ! Governorate ! Type ! Capacity (MW) ! Commission date ! Ref |
Aswan High Dam
| Aswan | Embankment | 2,100 | 1970 | |
Aswan Low Dam
| Aswan | Gravity | 592 | 1960 | |
Nag Hammadi Dam
| Qena | Gravity | 64 | 2008 | |
Nuclear
class="wikitable sortable"
! Name ! Operator ! Governorate ! Reactor type ! Capacity (MW) ! Commission date ! Ref |
El Dabaa Nuclear Power Plant
| | Matrouh | 4,800 | 2026 (expected) |
Oil- and gas-fired thermal
class="wikitable sortable"
! Name ! Operator ! Governorate ! Type ! Capacity (MW) ! Commission date ! Ref |
El Tebbin Power Station
| | Cairo | Thermal | 700 | 2010 | |
Abu Qir Power Plant
| | | 930 | 1991 | |
Ain Sokhna Power Plant
| | Suez | | 1,300 | 2014 | |
Cairo West Power Plant
| | Giza | | 1,360 | 2010 | |
Solar
Wind
class="wikitable sortable"
! Name ! Operator ! Governorate ! Type ! Capacity (MW) ! Commission date ! Ref |
Zafarana Wind Farms
| NREA{{ref label|NREA|f}} | 545 | 2001 |
Jabal Al-Zayt wind farm
| NREA{{ref label|NREA|f}} | 220 (580 MW when completed) | 2018 |
{{note|NREA}}New and Renewable Energy Authority
See also