Tennessee Valley Authority
{{short description|American utility company}}
{{redirect|TVA}}
{{use mdy dates|date=November 2020}}
{{Infobox company
| name = Tennessee Valley Authority
| logo = File:US-TennesseeValleyAuthority-Logo.svg
Logo of the TVA
File:Flag of the Tennessee Valley Authority.svg
Flag of the TVA
| image = {{photomontage
| photo1a = TVA-towers-tennessee-river-tn1.jpg
| photo1b = TVA offices in Chattanooga, Tennessee (4403311112).jpg
| photo2a = TVA map.png
| spacing = 1
| color_border = white
| color = white
| size = 310
}}
| image_size = 300px
| image_caption = From top down and left to right: TVA's twin tower administrative headquarters in Knoxville, TVA's power operations headquarters in Chattanooga, and a map of TVA's service area
| type = State-owned enterprise
| slogan =
| foundation = {{Start date|1933|05|18}}
| founders = * Harcourt Morgan
| location = Knoxville, Tennessee, U.S.
| industry = Electric utility
| revenue = {{decrease}} US$12.05 billion (2023)
| operating income =
| net_income = {{decrease}} US$0.5 billion (2023)
| owner = Federal government of the United States
| homepage = {{URL|www.tva.com|tva.com}}
}}
The Tennessee Valley Authority (TVA) is a federally owned electric utility corporation in the United States. TVA's service area covers all of Tennessee, portions of Alabama, Mississippi, and Kentucky, and small areas of Georgia, North Carolina, and Virginia. While owned by the federal government, TVA receives no taxpayer funding and operates similarly to a private for-profit company. It is headquartered in Knoxville, Tennessee, and is the sixth-largest power supplier and largest public utility in the country.{{cite news |last1=Sainz |first1=Adrian |title=Nation's largest utility in long-term deals to sell power |url=https://abcnews.go.com/US/wireStory/nations-largest-utility-long-term-deals-sell-power-67021289 |access-date=July 4, 2021 |work=ABC News |agency=Associated Press |date=November 14, 2019 |archive-date=July 9, 2021 |archive-url=https://web.archive.org/web/20210709182851/https://abcnews.go.com/US/wireStory/nations-largest-utility-long-term-deals-sell-power-67021289 |url-status=live }}
The TVA was created by Congress in 1933 as part of President Franklin D. Roosevelt's New Deal. Its initial purpose was to provide navigation, flood control, electricity generation, fertilizer manufacturing, regional planning, and economic development to the Tennessee Valley, a region that had suffered from lack of infrastructure and even more extensive poverty during the Great Depression than other regions of the nation. TVA was envisioned both as a power supplier and a regional economic development agency that would work to help modernize the region's economy and society. It later evolved primarily into an electric utility.{{sfn|Neuse|2004|pp=972–979}} It was the first large regional planning agency of the U.S. federal government, and remains the largest.
Under the leadership of David E. Lilienthal, the TVA also became the global model for the United States' later efforts to help modernize agrarian societies in the developing world.{{cite journal |last1=Ekbladh |first1=David |title="Mr. TVA": Grass-Roots Development, David Lilienthal, and the Rise and Fall of the Tennessee Valley Authority as a Symbol for U.S. Overseas Development, 1933–1973 |journal=Diplomatic History |date=Summer 2002 |volume=26 |issue=3 |pages=335–374 |doi=10.1111/1467-7709.00315 |issn=1467-7709 |oclc=772657716}}{{cite web |title=Global Impact |url=https://s25.q4cdn.com/191816265/files/doc_downloads/irw/tva_bonds/1998-h.pdf |website=Tennessee Valley Authority |access-date=May 17, 2021 |archive-date=May 17, 2021 |archive-url=https://web.archive.org/web/20210517153841/https://s25.q4cdn.com/191816265/files/doc_downloads/irw/tva_bonds/1998-h.pdf |url-status=live }} The TVA historically has been documented as a success in its efforts to modernize the Tennessee Valley and helping to recruit new employment opportunities to the region. Historians have criticized its use of eminent domain and the displacement of over 125,000 Tennessee Valley residents to build the agency's infrastructure projects.{{cite web |title=The Price of Power: How the Tennessee Valley Authority Impacted Attitudes Towards Economic Development in East Tennessee |url=https://appalachianfreepress.com/issue-%234/f/the-price-of-power |website=Appalachian Free Press |access-date=February 20, 2022 |date=January 12, 2022 |archive-date=February 18, 2022 |archive-url=https://web.archive.org/web/20220218191130/https://appalachianfreepress.com/issue-%234/f/the-price-of-power |url-status=dead }}
Operation
The Tennessee Valley Authority is a government-owned corporation created by U.S. Code Title 16, Chapter 12A, the Tennessee Valley Authority Act of 1933. It was initially founded as an agency to provide general economic development to the region through power generation, flood control, navigation assistance, fertilizer manufacturing, and agricultural development. Since the Depression years, it has developed primarily into a power utility. Despite its shares being owned by the federal government, TVA operates like a private corporation, and receives no taxpayer funding.{{cite web |url=https://www.tva.com/About-TVA |title=About TVA |author= |date=2018 |website=tva.com |publisher=Tennessee Valley Authority |access-date=January 7, 2018 |archive-date=December 6, 2017 |archive-url=https://web.archive.org/web/20171206031147/https://www.tva.com/About-TVA |url-status=live }} The TVA Act authorizes the company to use eminent domain.{{cite web |url=https://www.archives.gov/education/lessons/tva-relocation.html |title=The TVA and the Relocation of Mattie Randolph |author= |date= |website=Archives.gov |publisher=National Archives and Records Administration |access-date=March 4, 2019 |archive-date=March 6, 2019 |archive-url=https://web.archive.org/web/20190306043717/https://www.archives.gov/education/lessons/tva-relocation.html |url-status=live }}
TVA provides electricity to approximately ten million people through a diverse portfolio that includes nuclear, coal-fired, natural gas-fired, hydroelectric, and renewable generation. TVA sells its power to 153 local power utilities, 58 direct-serve industrial and institutional customers, 7 federal installations, and 12 area utilities.{{cite web |url=https://www.tva.com/Energy/Public-Power-Partnerships |title=Public Power Partnerships |author= |date=2018 |website=tva.com |publisher=Tennessee Valley Authority |access-date=January 7, 2019 |archive-date=April 12, 2019 |archive-url=https://web.archive.org/web/20190412051448/https://www.tva.com/Energy/Public-Power-Partnerships |url-status=live }} In addition to power generation, TVA provides flood control with its 29 hydroelectric dams. Resulting lakes and other areas also allow for recreational activities. The TVA also provides navigation and land management along rivers within its region of operation, which is the fifth-largest river system in the United States, and assists governments and private companies on economic development projects.
TVA's headquarters are located in Downtown Knoxville, with large administrative offices in Chattanooga (training/development; supplier relations; power generation and transmission) and Nashville (economic development) in Tennessee and Muscle Shoals, Alabama. TVA's headquarters were housed in the Old Customs House in Knoxville from 1936 until 1976, when the current complex opened. The building is now operated as a museum and is listed on the National Register of Historic Places.{{cite web |url=http://www.east-tennessee-history.org/ |title=East Tennessee Historical Society |publisher=East-tennessee-history.org |access-date=February 28, 2012 |url-status=dead |archive-url=https://web.archive.org/web/20070630145820/http://www.east-tennessee-history.org/ |archive-date=June 30, 2007}}
The Tennessee Valley Authority Police is the primary law enforcement agency for the company. Initially part of the TVA, in 1994 the TVA Police was authorized as a federal law enforcement agency.
=Board of directors=
The Tennessee Valley Authority is governed by a nine-member part-time board of directors, nominated by the president of the United States and confirmed by the Senate. A minimum of seven of the directors are required to be residents of TVA's service area. The members select the chair from their number, and serve five-year terms.{{efn|When their terms expire, directors may remain on the board until the end of the current congressional session (typically in December) or until their successors take office, whichever comes first.}} They receive annual stipends of $45,000 ($50,000 for the chair). The board members choose the TVA's chief executive officer.{{cite news |date=November 20, 2004 |title=TVA Board Expanded To 9 Members |url=https://www.chattanoogan.com/2004/11/20/58934/TVA-Board-Expanded-To-9-Members.aspx |work=The Chattanoogan |location=Chattanooga, Tennessee |access-date=January 7, 2019 |archive-date=January 7, 2019 |archive-url=https://web.archive.org/web/20190107181119/https://www.chattanoogan.com/2004/11/20/58934/TVA-Board-Expanded-To-9-Members.aspx |url-status=live }} When their terms expire, directors may remain on the board until the end of the current congressional session (typically in December) or until their successors take office, whichever comes first.
=Board members=
The current board members {{as of|lc=y|df=US|2025|05|09}}:
class="wikitable sortable plainrowheaders" style="text-align:center" |
scope="col" "width:15%" | Position
! scope="col" "width:15%" | Name ! scope="col" "width:15%" | State ! scope="col" "width:20%" | Appointed by ! scope="col" "width:15%" | Sworn in ! scope="col" "width:20%" | Term expires |
---|
Chairman
! scope="row" style="text-align:center;" |William J. Renick | {{dts|2023|01|04}} | May 18, 2027 |
Member
! scope="row" style="text-align:center;" | {{sortname|Beth Prichard|Geer}} | Joe Biden | {{dts|2023|01|04}} | {{dts|2026|05|18}} |
Member
! scope="row" style="text-align:center;"| {{sortname|Robert P.|Klein}} | Joe Biden | {{dts|2023|01|04}} | {{dts|2026|05|18}} |
Member
! scope="row" style="text-align:center;"| {{sortname|Adam Wade|White}} | Georgia | Joe Biden | {{dts|2023|01|04}} | May 18, 2027 |
Member
! scope="row" style="text-align:center;" | Vacant | | | | May 18, 2025 |
Member
! scope="row" style="text-align:center;" | Vacant | | | | {{dts|2027|05|18}} |
Member
! scope="row" style="text-align:center;" | Vacant | | | | {{dts|2028|05|18}} |
Member
! scope="row" style="text-align:center;" | Vacant | | | | {{dts|2029|05|18}} |
Member
! scope="row" style="text-align:center;" | Vacant | | | | {{dts|2029|05|18}} |
= Power generation =
== Power stations ==
{{main|List of power stations operated by the Tennessee Valley Authority}}
With a generating capacity of approximately 35 gigawatts (GW), TVA has the sixth highest generation capacity of any utility company in the United States and the third largest nuclear power fleet, with seven units at three sites.{{cite news |url=https://www.reuters.com/article/amp/idUSBREA3S0P420140429 |title=Factbox: Largest U.S. electric companies by megawatts, customers |author= |date=April 29, 2014 |work=Reuters |access-date=January 7, 2019 |archive-date=March 8, 2021 |archive-url=https://web.archive.org/web/20210308123918/https://www.reuters.com/article/amp/idUSBREA3S0P420140429 |url-status=live }}{{cite news |last=McDermott |first=Jennifer |date=February 10, 2022 |title=Largest US public power company launches new nuclear program |url=https://apnews.com/article/climate-technology-business-lifestyle-kentucky-28d44198e92e4d1aaf6ebcf223c50a19 |work=Associated Press News |access-date=March 18, 2023 |archive-date=March 18, 2023 |archive-url=https://web.archive.org/web/20230318083806/https://apnews.com/article/climate-technology-business-lifestyle-kentucky-28d44198e92e4d1aaf6ebcf223c50a19 |url-status=live }} In addition, they also operate four coal-fired power plants, 29 hydroelectric dams, nine simple-cycle natural gas combustion turbine plants, nine combined cycle gas plants, 1 pumped storage hydroelectric plant, 1 wind energy site, and 14 solar energy sites. In fiscal year 2020, nuclear generation made up about 41% of TVA's total energy production, natural gas 26%, coal 14%, hydroelectric 13%, and wind and solar 3%.{{cite web |url=https://www.tva.com/Energy/Our-Power-System |title=Our Power System |date=2018 |website=tva.com |publisher=Tennessee Valley Authority |access-date=January 7, 2019 |archive-date=April 12, 2019 |archive-url=https://web.archive.org/web/20190412041402/https://www.tva.com/Energy/Our-Power-System |url-status=live }} TVA purchases about 15% of the power it sells from other power producers, which includes power from combined cycle natural gas plants, coal plants, and wind installations, and other renewables.{{cite web |url=https://www.tva.com/power/wind_purchases.htm |title=TVA: Energy Purchases from Wind Farms |work=TVA |url-status=dead |archive-url=https://web.archive.org/web/20150731021622/https://www.tva.com/power/wind_purchases.htm |archive-date=July 31, 2015}} The cost of Purchased Power is part of the "Fuel Cost Adjustment" (FCA) charge that is separate from the TVA Rate. In addition, the Watts Bar Nuclear Plant is the only facility in the country to industrially produce tritium, which is used by the National Nuclear Security Administration for nuclear weapons, where it is used to supercharge and boost the explosive yield of the U.S. nuclear arsenal.{{cite news |last=Cathey |first=Ben |date=May 24, 2022 |title=Watts Bar lone source of a nuclear weapon material; TVA increasing production |url=https://www.wvlt.tv/2022/05/24/watts-bar-lone-source-nuclear-weapon-material-tva-increasing-production/ |work=WVLT-TV |location=Knoxville |access-date= |archive-date=March 18, 2023 |archive-url=https://web.archive.org/web/20230318084551/https://www.wvlt.tv/2022/05/24/watts-bar-lone-source-nuclear-weapon-material-tva-increasing-production/ |url-status=live }}
== Electric transmission ==
TVA owns and operates its own electric grid, which consists of approximately {{convert|16,200|mi}} of lines, one of the largest grids in the United States. This grid is part of the Eastern Interconnection of the North American power transmission grid, and is under the jurisdiction of the SERC Reliability Corporation.{{cite web |url=https://www.eia.gov/todayinenergy/detail.php?id=27152 |title=U.S. electric system is made up of interconnections and balancing authorities |author= |date=July 20, 2016 |website=eia.gov |publisher=Energy Information Administration |access-date=January 2, 2022 |archive-date=January 2, 2022 |archive-url=https://web.archive.org/web/20220102031128/https://www.eia.gov/todayinenergy/detail.php?id=27152 |url-status=live }} Like most North American utilities, TVA uses a maximum transmission voltage of 500 kilovolts (kV), with lines carrying this voltage using bundled conductors with three conductors per phase. The vast majority of TVA's transmission lines carry 161 kV, with the company also operating a number of sub-transmission lines with voltages of 69 kV and 46kV. They also operate a small number of 115kV and 230kV lines in Alabama and Georgia that connect to Southern Company lines of the same voltage.{{cite report|last1=Clem|first1=Clayton L.|last2=Nelson|first2=Jeffrey H.|title=2010 International Conference on High Voltage Engineering and Application|date=October 2010|chapter=The TVA Transmission System: Facts, Figures and Trends|pages=1–11|chapter-url=https://zenodo.org/record/1270775|publisher=Proceedings of the 2010 IEEE International Conference on High Voltage Engineering and Application|doi=10.1109/ichve.2010.5640878|isbn=978-1-4244-8283-2|access-date=2021-04-18|via=Zenodo|archive-date=June 24, 2021|archive-url=https://web.archive.org/web/20210624202734/https://zenodo.org/record/1270775|url-status=live}}{{Cite map |year = 2011 |title = NERC Transmission Planning Map |url = http://www.oatioasis.com/TVA/TVAdocs/TVA_Transmission_Map_2011_r2.pdf |publisher = North American Electric Reliability Corporation |access-date= 2021-04-18 |via = Open Access Same-Time Information System |url-status=dead |archive-url=https://web.archive.org/web/20160909085921/http://www.oatioasis.com/TVA/TVAdocs/TVA_Transmission_Map_2011_r2.pdf |archive-date=September 9, 2016 }}
= Recreation =
TVA has conveyed approximately {{convert|485,420|acres|km2}} of property for recreation and preservation purposes including public parks, public access areas and roadside parks, wildlife refuges, national parks and forests, and other camps and recreation areas, comprising approximately 759 different sites.{{cite web |title=Chapter 8 – Recreation Management |work=Natural Resource Plan |publisher=Tennessee Valley Authority |url=http://www.tva.gov/environment/reports/nrp/pdf/finals/nrp_chapter5.pdf |access-date=March 22, 2012 |page=113 |date=July 2011 |url-status=dead |archive-url=https://web.archive.org/web/20111110191237/http://www.tva.gov/environment/reports/nrp/pdf/finals/nrp_chapter5.pdf |archive-date=November 10, 2011}}
Currently, TVA manages approximately {{convert|293,000|acres|km2}} of Federally-owned land for public use. These lands are managed as either TVA Natural Areas or TVA Day-Use Recreation Areas. Natural Areas are smaller, ecologically or historically significant areas set aside for conservation, with some areas including hiking and walking trails. Day-Use Recreation Areas comprise approximately 80 different locations throughout the Tennessee Valley largely concentrated on or near TVA reservoirs that include water access points, campgrounds, hiking trails, fishing piers, and equestrian facilities.{{cite web |title=Day-Use Recreation Areas |url=https://www.tva.com/environment/recreation/day-use-recreation-areas |website=TVA.com |publisher=Tennessee Valley Authority |access-date=June 6, 2023 |archive-date=June 6, 2023 |archive-url=https://web.archive.org/web/20230606173200/https://www.tva.com/environment/recreation/day-use-recreation-areas |url-status=live }}{{cite web |title=Small Wild Areas |url=https://www.tva.com/environment/recreation/small-wild-areas |website=TVA.com |publisher=Tennessee Valley Authority |access-date=6 June 2023 |archive-date=June 6, 2023 |archive-url=https://web.archive.org/web/20230606173201/https://www.tva.com/environment/recreation/small-wild-areas |url-status=live }}
= Economic development =
TVA operates an economic development organization that works with companies and economic development agencies throughout the Tennessee Valley to create jobs via private investments. They also work with businesses to help them choose locations for facilities and expand existing facilities. Services provided include assistance with site selection, employee recruitment and training, and research.{{cite web |url=https://www.tva.com/economic-development/the-global-valley |title=The Global Valley |author= |date= |publisher=Tennessee Valley Authority |access-date=March 18, 2023 |archive-date=March 18, 2023 |archive-url=https://web.archive.org/web/20230318100834/https://www.tva.com/economic-development/the-global-valley |url-status=live }} A total of seven sites throughout the Valley are certified by TVA as megasites, which contain a minimum of {{convert|1,000|acre|km2}}, and have access to an Interstate Highway and the potential for rail service, and environmental impact study, and contain or have the potential to contain direct-serve industrial customers.{{cite news |last1=Mattson-Teig |first1=Beth |title=Mega Sites Lure Big Fish |journal=Area Development |date=Summer 2013 |url=https://www.areadevelopment.com/siteSelection/Q3-2013/megasites-1000-plus-acre-certified-sites-182827611.shtml |access-date=March 19, 2018 |archive-date=June 12, 2017 |archive-url=https://web.archive.org/web/20170612173742/http://www.areadevelopment.com/siteSelection/Q3-2013/megasites-1000-plus-acre-certified-sites-182827611.shtml |url-status=live }}
History
= Background =
In the late 19th century, the Army Corps of Engineers first recognized a number of potential dam sites along the Tennessee River for electricity generation and navigation improvements.{{sfn|Hargrove|1994|p=19}} The National Defense Act of 1916, signed into law by President Woodrow Wilson, authorized the construction of a hydroelectric dam on the Tennessee River in Muscle Shoals, Alabama, for the purpose of producing nitrates for ammunition; that dam was completed in 1924.
During the 1920s and the 1930s, Americans began to support the idea of public ownership of utilities, particularly hydroelectric power facilities. Many believed privately owned power companies were charging too much for power, did not employ fair operating practices, and were subject to abuse by their owners, utility holding companies, at the expense of consumers.{{citation needed|date=May 2021}} The concept of government-owned generation facilities selling to publicly owned distribution utilities was controversial, and remains so today.{{cite book |last1=Hubbard |first1=Preston J. |title=Origins of the TVA: The Muscle Shoals Controversy, 1920–1932 |date=1961 |publisher=Vanderbilt University Press |location=Nashville |oclc=600647072 |url=https://babel.hathitrust.org/cgi/pt?id=mdp.39015031695052;view=1up;seq=12 |pages=189–194 |via=HathiTrust Digital Library |access-date=March 20, 2018 |archive-date=March 7, 2021 |archive-url=https://web.archive.org/web/20210307215550/https://babel.hathitrust.org/cgi/pt?id=mdp.39015031695052;view=1up;seq=12 |url-status=live }} The private sector practice of forming utility holding companies had resulted in them controlling 94 percent of generation by 1921, and they were essentially unregulated. In an effort to change this, Congress and Roosevelt enacted the Public Utility Holding Company Act of 1935 (PUHCA).{{cite journal |last=Hawes |first=Douglas W. |date=April 1977 |title=Public Utility Holding Company Act of 1935 -- Fossil or Foil? |url=https://scholarship.law.vanderbilt.edu/cgi/viewcontent.cgi?article=3108&context=vlr |journal=Vanderbilt Law Review |volume=30 |issue=3 |pages=605–625 |doi= |access-date=March 12, 2023 |archive-date=March 12, 2023 |archive-url=https://web.archive.org/web/20230312064455/https://scholarship.law.vanderbilt.edu/cgi/viewcontent.cgi?article=3108&context=vlr |url-status=live }}
During his 1932 presidential campaign, Franklin D. Roosevelt expressed his belief that private utilities had "selfish purposes" and said, "Never shall the federal government part with its sovereignty or with its control of its power resources while I'm President of the United States."
U.S. Senator George W. Norris of Nebraska also distrusted private utility companies, and in 1920 blocked a proposal from industrialist Henry Ford to build a private dam and create a utility to modernize the Tennessee Valley.{{cite book|last=Tobey|first=Ronald C.|title=Technology as Freedom: The New Deal and the Electrical Modernization of the American Home|url=https://books.google.com/books?id=0geUkFJjbzEC&pg=PA46|year=1996|publisher=University of California Press|pages=46–48|isbn=9780520204218 |access-date=2021-07-04|via=Google Books}} In 1930, Norris sponsored the Muscle Shoals Bill, which would have built a federal dam in the valley, but it was vetoed by President Herbert Hoover, who believed it to be socialistic.{{Cite news|date=April 5, 1930|title=Muscle Shoals Bill Passed By Senate; Vote on Norris Measure for Operation by Federal Corporation Is 45 to 23. House Counted Favorable But Hoover Veto is Expected in Event of Passage—His Supporters Divided in Debate. Hoover Supporters Divided. The Vote on Roll-Call.|work=The New York Times|page=3|url=https://www.nytimes.com/1930/04/05/archives/muscle-shoals-bill-passed-by-senate-vote-on-norris-measure-for.html|access-date=September 14, 2021|issn=0362-4331|archive-date=September 14, 2021|archive-url=https://web.archive.org/web/20210914152526/https://www.nytimes.com/1930/04/05/archives/muscle-shoals-bill-passed-by-senate-vote-on-norris-measure-for.html|url-status=live}}
The idea behind the Muscle Shoals project became a core part of President Franklin D. Roosevelt's New Deal program that created the Tennessee Valley Authority.{{cite journal |last1=Wengert |first1=Norman |title=Antecedents of TVA: The Legislative History of Muscle Shoals |journal=Agricultural History |date=1952 |volume=26 |issue=4 |pages=141–147 |issn=1533-8290 |oclc=971899953 |jstor=3740474}}
Even by Depression standards, the Tennessee Valley was in dire economic straits in 1933. Thirty percent of the population was affected by malaria. The average income in the rural areas was $639 per year (equivalent to ${{formatprice|{{inflation|US-GDP|639|1933}}}} in {{CURRENTYEAR}}),{{inflation-fn|US-GDP}} with some families surviving on as little as $100 per year (equivalent to ${{formatprice|{{inflation|US-GDP|100|1933}}}} in {{inflation-year|US-GDP}}).{{inflation-fn|US-GDP}}
Much of the land had been exhausted by poor farming practices, and the soil was eroded and depleted. Crop yields had fallen, reducing farm incomes. The best timber had been cut, and 10% of forests were lost to fires each year.
= Founding and early history =
File:Roosevelt signing TVA Act (1933).jpg signing the TVA Act]]
File:TVA sign at Hyde Park, NY IMG 5665.JPG]]
President Franklin Delano Roosevelt signed the Tennessee Valley Authority Act (ch. 32, {{USStatute|73|17|48|58|1933|05|18}}, codified as amended at {{USC|16|831}}, et seq.), creating the TVA. The agency was initially tasked with modernizing the region, using experts and electricity to combat human and economic problems.{{cite book |last1=Schulman |first1=Bruce J. |title=From Cotton Belt to Sunbelt: Federal policy, economic development, and the transformation of the South, 1938–1980 |date=1991 |publisher=Oxford University Press |location=New York |oclc=300412389 |isbn=978-0-19-536344-9}} TVA developed fertilizers, and taught farmers ways to improve crop yields. In addition, it helped replant forests, control forest fires, and improve habitats for fish and wildlife.
The Authority hired many of the area's unemployed for a variety of jobs: they conducted conservation, economic development, and social programs. For instance, a library service was instituted for this area. The professional staff at headquarters were generally composed of experts from outside the region. By 1934, TVA employed more than 9,000 people.{{cite web |url=https://www.history.com/topics/great-depression/history-of-the-tva |title=TVA |author= |date=August 7, 2017 |website=History.com |publisher=The History Channel |access-date=January 8, 2019 |archive-date=January 8, 2019 |archive-url=https://web.archive.org/web/20190108200728/https://www.history.com/topics/great-depression/history-of-the-tva |url-status=live }} The workers were classified by the usual racial and gender lines of the region, which limited opportunities for minorities and women. TVA hired a few African Americans, generally restricted for janitorial or other low-level positions. TVA recognized labor unions; its skilled and semi-skilled blue collar employees were unionized, a breakthrough in an area known for corporations hostile to miners' and textile workers' unions. Women were excluded from construction work.
File:TVA-first-board.jpg, Arthur E. Morgan, and David E. Lilienthal]]
Many local landowners were suspicious of government agencies, but TVA successfully introduced new agricultural methods into traditional farming communities by blending in and finding local champions. Tennessee farmers often rejected advice from TVA officials, so the officials had to find leaders in the communities and convince them that crop rotation and the judicious application of fertilizers could restore soil fertility.{{cite journal |last1=Shapiro |first1=Edward |title=The Southern Agrarians and the Tennessee Valley Authority |journal=American Quarterly |date=Winter 1970 |volume=22 |issue=4 |pages=791–806 |doi=10.2307/2711870 |issn=0003-0678 |oclc=5545493875 |jstor=2711870}} Once they had convinced the leaders, the rest followed.{{cite book |last=Selznick |first=Philip |author-link=Philip Selznick |date=1953 |title=TVA and the Grass Roots: A Study in the Sociology of Formal Organization |url=https://books.google.com/books?id=Mym5Ycgamo8C |location=Los Angeles; Berkeley, California |publisher=University of California Press |pages=134–139 |isbn=1528359852 |access-date=March 19, 2023 |archive-date=October 6, 2023 |archive-url=https://web.archive.org/web/20231006212651/https://books.google.com/books?id=Mym5Ycgamo8C |url-status=live }}
File:"A group showing some of the men working at Norris Dam." - NARA - 532717.jpg, the first hydroelectric dam built by the TVA, {{Circa|1933}}]]
TVA immediately embarked on the construction of several hydroelectric dams, with the first, Norris Dam in upper East Tennessee, breaking ground on October 1, 1933. These facilities, designed with the intent of also controlling floods, greatly improved the lives of farmers and rural residents, making their lives easier and farms in the Tennessee Valley more productive. They also provided new employment opportunities to the poverty-stricken regions in the Valley. At the same time, however, they required the displacement of more than 125,000 valley residents or roughly 15,000 families, as well as some cemeteries and small towns, which caused some to oppose the projects, especially in rural areas.{{cite book |last1=Muldowny |first1=John |last2=McDonald |first2=Michael |title=TVA and the Dispossessed: The Resettlement of Population in the Norris Dam Area |date=1981 |publisher=University of Tennessee Press |isbn=9781572331648 |url=https://books.google.com/books?id=_vUrhbkRLiAC |access-date=July 4, 2021 |archive-date=January 11, 2023 |archive-url=https://web.archive.org/web/20230111024357/https://www.google.com/books/edition/TVA_and_the_Dispossessed/_vUrhbkRLiAC?hl=en&gbpv=0 |url-status=live }}{{cite web |last1=Stephens |first1=Joseph |title=Forced Relocations Presented More of an Ordeal than an Opportunity for Norris Reservoir Families |url=https://www.historicunioncounty.com/article/forced-relocations-presented-more-ordeal-opportunity-norris-reservoir-families |website=Historic Union County |date=May 2018 |access-date=June 15, 2021 |archive-date=July 9, 2021 |archive-url=https://web.archive.org/web/20210709184540/https://www.historicunioncounty.com/article/forced-relocations-presented-more-ordeal-opportunity-norris-reservoir-families |url-status=live }} The projects also inundated several Native American archaeological sites, and graves were reinterred at new locations, along with new tombstones.{{sfn|Creese|1990|pp=95-105}}{{Cite web |title=Brackish Water |url=https://oxfordamerican.org/magazine/issue-125-summer-2024/brackish-water |access-date=2024-07-07 |website=Oxford American |language=en}}
The available electricity attracted new industries to the region, including textile mills, providing desperately needed jobs, many of which were filled by women.{{sfn|Neuse|2004|pp=972–979}}{{cite journal |last1=Long |first1=Jennifer |title=Government Job Creation Programs—Lessons from the 1930s and 1940s |journal=Journal of Economic Issues |date=December 1999 |volume=33 |issue=4 |pages=903–918 |issn=0021-3624 |doi=10.1080/00213624.1999.11506220 |oclc=5996637494}} A few regions of the Tennessee Valley did not receive electricity until the late 1940s and early 1950s, however. TVA was one of the first federal hydropower agencies, and was quickly hailed as a success. While most of the nation's major hydropower systems are federally managed today, other attempts to create similar regional corporate agencies have failed. The most notable was the proposed Columbia Valley Authority for the Columbia River in the Pacific Northwest, which was modeled off of TVA, but did not gain approval.{{sfn|Hargrove|1994|p=137}}
=World War II=
File:PalmercarpenterA.jpg, wearing a contractor's employee badge, at work during the 1942 construction of Douglas Dam in East Tennessee.]]
In order to provide the power for essential industries during World War II, TVA engaged in one of the largest hydropower construction programs ever undertaken in the U.S. This was especially important for the energy-intensive aluminum industry, which was used in airplanes and munitions.{{sfn|Russell|1949|pp=29-30}} By early 1942, when the effort reached its peak, 12 hydroelectric plants and one coal-fired steam plant were under construction at the same time, and design and construction employment reached a total of 28,000. In its first eleven years, TVA constructed a total of 16 hydroelectric dams. During the war, the agency also provided 60% of the elemental phosphorus used in munitions, produced maps of approximately {{convert|500,000|mi2|km2}} of foreign territory using aerial reconnaissance, and provided mobile housing for war workers.
The largest project of this period was the Fontana Dam. After negotiations led by then-Vice President Harry Truman, TVA purchased the land from Nantahala Power and Light, a wholly owned subsidiary of Alcoa, and built Fontana Dam. Also in 1942, TVA's first coal-fired plant, the 267-megawatt Watts Bar Steam Plant, began operation.{{cite web |url=https://www.tva.com/energy/our-power-system/coal/plants-of-the-past |title=Plants of the Past |website=tva.com |publisher=Tennessee Valley Authority |access-date=October 21, 2018 |archive-date=August 6, 2020 |archive-url=https://web.archive.org/web/20200806101408/https://www.tva.com/energy/our-power-system/coal/plants-of-the-past |url-status=live }} The government originally intended the electricity generated from Fontana to be used by Alcoa factories for the war effort. However, the abundance of TVA power was one of the major factors in the decision by the U.S. Army to locate uranium enrichment facilities in Oak Ridge, Tennessee, for the world's first atomic bombs.{{sfn|Russell|1949|pp=30-32}}{{sfn|Creese|1990|pp=221-231}} This was part of an effort codenamed the Manhattan Project.{{cite book |last1=Fine |first1=Lenore |last2=Remington |first2=Jesse A. |title=The Corps of Engineers: Construction in the United States |publisher=United States Army Center of Military History |url=http://www.history.army.mil/html/books/010/10-5/CMH_Pub_10-5.pdf |pages=134–135 |access-date=August 25, 2013 |location=Washington, D.C. |year=1972 |oclc=834187 |archive-date=February 1, 2017 |archive-url=https://web.archive.org/web/20170201142645/https://history.army.mil/html/books/010/10-5/CMH_Pub_10-5.pdf |url-status=dead }}{{cite book |last=Jones |first=Vincent |title=Manhattan: The Army and the Atomic Bomb |publisher=United States Army Center of Military History |location=Washington, D.C. |year=1985 |url=http://www.history.army.mil/html/books/011/11-10/CMH_Pub_11-10.pdf |pages=46–47 |access-date=25 August 2013 |oclc=10913875 |archive-date=October 7, 2014 |archive-url=https://web.archive.org/web/20141007074359/http://www.history.army.mil/html/books/011/11-10/CMH_Pub_11-10.pdf |url-status=dead }}
= Increasing power demand =
File:John Sevier Steam Plant - 1956.jpg in Hawkins County, Tennessee, {{circa|1956}}]]
By the end of World War II, TVA had completed a {{convert|650|mi|km|adj=on}} navigation channel the length of the Tennessee River and had become the nation's largest electricity supplier.{{sfn|Russell|1949|pp=23-24}} Even so, the demand for electricity was outstripping TVA's capacity to produce power from hydroelectric dams, and so TVA began to construct additional coal-fired plants. Political interference kept TVA from securing additional federal appropriations to do so, so it sought the authority to issue bonds.{{sfn|Hargrove|Conkin|1983|pp=75-76}} Several of TVA's coal-fired plants, including Johnsonville, Widows Creek, Shawnee, Kingston, Gallatin, and John Sevier, began operations in the 1950s.{{cite news |last=Gross |first=Daniel |date=October 2, 2015 |title=The Tennessee Valley Authority is closing coal plants, and that's huge |url=https://www.slate.com/business/2015/10/the-tennessee-valley-authority-is-closing-coal-plants-and-thats-huge. |work=Slate Magazine |access-date=January 7, 2019 }}{{Dead link|date=April 2024 |bot=InternetArchiveBot |fix-attempted=yes }} In 1955 coal surpassed hydroelectricity as TVA's top generating source.{{cite web |url=https://www.tva.com/About-TVA/Our-History/The-1950s |title=The 1950s |author= |date=2018 |website=tva.com |publisher=Tennessee Valley Authority |access-date=January 7, 2019 |archive-date=January 26, 2019 |archive-url=https://web.archive.org/web/20190126030936/https://www.tva.com/About-TVA/Our-History/The-1950s |url-status=live }} On August 6, 1959, President Dwight D. Eisenhower signed into law an amendment to the TVA act, making the agency self-financing.{{cite news |date=May 11, 2008 |title=Snapshot of major events in TVA history |url=https://archive.knoxnews.com/news/local/snapshot-of-major-events-in-tva-history-ep-411654928-359899091.html/?page=1 |work=The Knoxville News-Sentinel |access-date=January 20, 2019 |archive-date=January 20, 2019 |archive-url=https://web.archive.org/web/20190120194539/http://archive.knoxnews.com/news/local/snapshot-of-major-events-in-tva-history-ep-411654928-359899091.html/?page=1 |url-status=live }} During the 1950s, TVA's generating capacity nearly quadrupled.
The 1960s were years of further unprecedented economic growth in the Tennessee Valley. Capacity growth during this time slowed, but ultimately increased 56% between 1960 and 1970. To handle a projected future increase in electrical consumption, TVA began constructing 500 kilovolt (kV) transmission lines, the first of which was placed into service on May 15, 1965. Electric rates were among the nation's lowest during this time and stayed low as TVA brought larger, more efficient generating units into service. Plants completed during this time included Paradise, Bull Run, and Nickajack Dam. Expecting the Valley's electric power needs to continue to grow, TVA began building nuclear power plants in 1966 as a new source of power.{{cite web |url=https://tva.com/75th/pdf/tva_timeline_by_year.pdf |title=TVA timeline by year |publisher=Tennessee Valley Authority |access-date=August 5, 2009 |url-status=dead |archive-date=August 4, 2010 |archive-url=https://web.archive.org/web/20100804060602/http://www.tva.com/75th/pdf/tva_timeline_by_year.pdf}} The following year, TVA began work on the construction of Tellico Dam, which had been initially conceived in the 1930s and would later become its most controversial project.{{cite news |last=Morrissey |first=Connor |date=December 11, 2018 |title=The Tennessee Valley Authority: A Timeline of Controversy |url=https://medium.com/fall-2018-vt-intro-to-appalachian-studies/the-tennessee-valley-authority-a-timeline-of-controversy-b1a69df40a15 |work=Medium |access-date=June 2, 2020 |archive-date=July 26, 2022 |archive-url=https://web.archive.org/web/20220726012057/https://medium.com/fall-2018-vt-intro-to-appalachian-studies/the-tennessee-valley-authority-a-timeline-of-controversy-b1a69df40a15 |url-status=live }}{{cite news |last1=Rawls |first1=Wendell Jr. |title=Forgotten People of the Tellico Dam Fight |url=https://www.nytimes.com/1979/11/11/archives/forgotten-people-of-the-tellico-dam-fight-right-of-eminent-domain.html |access-date=April 18, 2021 |work=The New York Times |date=November 11, 1979 |page=1 |archive-date=July 26, 2022 |archive-url=https://web.archive.org/web/20220726020225/https://www.nytimes.com/1979/11/11/archives/forgotten-people-of-the-tellico-dam-fight-right-of-eminent-domain.html |url-status=live }}{{cite web |title=Telling the Story of Tellico: It's Complicated |url=https://www.tva.com/about-tva/our-history/built-for-the-people/telling-the-story-of-tellico-it-s-complicated |website=Tennessee Valley Authority |access-date=July 24, 2022 |url-status=live |archive-date=June 16, 2022 |archive-url=https://web.archive.org/web/20220616105923/https://www.tva.com/about-tva/our-history/built-for-the-people/telling-the-story-of-tellico-it-s-complicated}}
= Financial problems, Tellico Dam, and restructuring =
File:Land use plan of TVA's failed Timberlake City project.png along the Tellico Reservoir was proposed to support 30,000 residents.{{cite book |author1=Tennessee Valley Authority |title=Timberlake New Community: Final Environmental Statement |date=January 1, 1976 |publisher=Boston College Law School |location=Chattanooga |format=PDF |url=https://lawdigitalcommons.bc.edu/cgi/viewcontent.cgi?article=1040&context=darter_materials |access-date=August 11, 2021 |archive-date=August 12, 2022 |archive-url=https://web.archive.org/web/20220812141123/https://lawdigitalcommons.bc.edu/cgi/viewcontent.cgi?article=1040&context=darter_materials |url-status=live }} The project was cancelled soon after the Tellico Project's controversy.{{cite web |last1=Van West |first1=Carroll |title=Monroe County |url=https://tennesseeencyclopedia.net/entries/monroe-county/ |website=Tennessee Encyclopedia |publisher=Tennessee Historical Society |access-date=August 11, 2021 |date=October 8, 2017 |archive-date=August 9, 2022 |archive-url=https://web.archive.org/web/20220809070351/https://tennesseeencyclopedia.net/entries/monroe-county/ |url-status=live }}]]
During the 1970s significant changes occurred in the economy of the Tennessee Valley and the nation, prompted by energy crises in 1973 and 1979 and accelerating fuel costs throughout the decade. The average cost of electricity in the Tennessee Valley increased fivefold from the early 1970s to the early 1980s. TVA's first nuclear reactor, Browns Ferry Unit 1, began commercial operation on August 1, 1974.{{cite news|author=|title=Browns Ferry No. 2 N-Unit Test Approved|url=https://tennessean.newspapers.com/clip/57880858/browns-ferry-no-2-n-unit-test-approved/|page=6|work=The Tennessean|location=Nashville, Tennessee|agency=Associated Press|date=August 9, 1974|access-date=2020-08-23|via=Newspapers.com|archive-date=April 18, 2021|archive-url=https://web.archive.org/web/20210418203709/https://tennessean.newspapers.com/clip/57880858/browns-ferry-no-2-n-unit-test-approved/|url-status=live}} Between 1970 and 1974, TVA set out to construct a total of 17 nuclear reactors, due to a projection of further rapid increase in power demand.{{cite news |url=https://www.nytimes.com/2011/08/19/science/earth/19nuclear.html |title=Alabama Nuclear Reactor, Partly Built, to Be Finished |first=Matthew |last=Wald |date=August 19, 2011 |work=The New York Times |page=A12 |access-date=February 25, 2017 |archive-date=August 12, 2017 |archive-url=https://web.archive.org/web/20170812191546/http://www.nytimes.com/2011/08/19/science/earth/19nuclear.html? |url-status=live }} However, in the 1980s, it became increasingly evident that the agency had vastly overestimated the Valley's future energy needs, and rapid increases in construction costs and new regulations following the Three Mile Island accident posed additional obstacles to this undertaking.{{cite news |last=Labaton |first=Stephen |date=August 3, 1985 |title=Tennessee Valley Authority Generates Woes With Nuclear Power Program |url=https://www.washingtonpost.com/archive/politics/1985/08/03/tennessee-valley-authority-generates-woes-with-nuclear-power-program/de3b0602-e769-4cb8-b351-73c49850fea6/ |newspaper=The Washington Post |access-date=March 18, 2023}}{{cite news |last=Davis |first=Will |date=April 17, 2015 |title=TVA Prepares to Write Final Nuclear Chapters |url=https://www.ans.org/news/article-1686/tva-prepares-to-write-final-nuclear-chapters/ |work=Nuclear Newswire |publisher=American Nuclear Society |access-date=March 18, 2023 |archive-date=July 29, 2023 |archive-url=https://web.archive.org/web/20230729001150/https://www.ans.org/news/article-1686/tva-prepares-to-write-final-nuclear-chapters/ |url-status=live }} In 1981, the board voted to defer the Phipps Bend plant, as well as to slow down construction on all other projects.{{cite news |url=https://www.timesnews.net/News/2008/08/23/Nuclear-power-option-still-alive-at-TVA-despite-Phipps-Bend-debacle |title=Nuclear power option still alive at TVA despite Phipps Bend debacle |work=Kingsport Times-News |access-date=December 31, 2017 |first=Hank |last=Hayes |date=August 23, 2008 |archive-date=January 1, 2018 |archive-url=https://web.archive.org/web/20180101030650/http://www.timesnews.net/News/2008/08/23/Nuclear-power-option-still-alive-at-TVA-despite-Phipps-Bend-debacle |url-status=live }} The Hartsville and Yellow Creek plants were cancelled in 1984 and Bellefonte in 1988. Citing safety concerns, all of TVAs five operating nuclear reactors were indefinitely shut down in 1985 with the two at Sequoyah coming back online three years later and Browns Ferry's three reactors coming back online in 1991, 1995 and 2007. {{cite news |date=August 22, 1985 |title=T.V.A., Citing Safety, to Shut Down Nuclear Plant |work=The New York Times |page=A19 |agency=Associated Press |url=https://www.nytimes.com/1985/08/22/us/tva-citing-safety-to-shut-down-nuclear-plant.html |access-date=2019-01-07 |archive-date=March 18, 2023 |archive-url=https://web.archive.org/web/20230318072631/https://www.nytimes.com/1985/08/22/us/tva-citing-safety-to-shut-down-nuclear-plant.html |url-status=live }}
File:Early Tellico Dam Construction.jpg
Construction of the Tellico Dam raised political and environmental concerns, as laws had changed since early development in the valley. Scientists and other researchers had become more aware of the massive environmental effects of the dams and new lakes, and worried about preserving habitats and species. The Tellico Dam project was initially delayed because of concern over the snail darter, a small ray-finned fish which had been discovered in the Little Tennessee River in 1973 and listed as an endangered species two years later.{{cite news |last1=Wilson |first1=Robert |date=April 13, 2008 |title=Tellico Dam still generating debate |url=https://archive.knoxnews.com/business/tellico-dam-still-generating-debate-ep-411807529-359923851.html/ |access-date=July 24, 2022 |work=Knoxville News Sentinel |archive-date=October 13, 2016 |archive-url=https://web.archive.org/web/20161013142515/http://archive.knoxnews.com/business/tellico-dam-still-generating-debate-ep-411807529-359923851.html |url-status=live}} A lawsuit was filed under the Endangered Species Act and the U.S. Supreme Court ruled in favor of protecting the snail darter in Tennessee Valley Authority v. Hill in 1978.{{cite court |litigants=Tennessee Valley Authority v. Hill |vol=437 |reporter=U.S. |opinion=153 |court=U.S. Supreme Court |date=June 15, 1978 |url=https://supreme.justia.com/cases/federal/us/437/153/ |access-date=May 8, 2020 |archive-url=https://web.archive.org/web/20200519222539/https://supreme.justia.com/cases/federal/us/437/153/ |url-status=live }} The project's main motive was to support recreational and tourism development, unlike earlier dams constructed by TVA. Land acquired by eminent domain for the Tellico Dam and its reservoir that encountered minimal inundation was sold to private developers for the construction of present-day Tellico Village, a planned retirement community.{{cite news |last1=Rawls |first1=Wendell |title=Forgotten People of the Tellico Dam Fight |work=The New York Times |date=November 11, 1979 |url=https://www.nytimes.com/1979/11/11/archives/forgotten-people-of-the-tellico-dam-fight-right-of-eminent-domain.html |access-date=July 4, 2021 |archive-date=July 26, 2022 |archive-url=https://web.archive.org/web/20220726020225/https://www.nytimes.com/1979/11/11/archives/forgotten-people-of-the-tellico-dam-fight-right-of-eminent-domain.html |url-status=live }}
The inflation crises of the 1970s and early 1980s, combined with the cancellation of several of the planned nuclear plants put the agency in deep financial trouble.{{cite news |last=Smothers |first=Ronald |date=June 30, 1988 |title=T.V.A. Slashes Work Force And Holds Off on 2 Plants |url=https://www.nytimes.com/1988/06/30/us/tva-slashes-work-force-and-holds-off-on-2-plants.html |page=A-14 |work=The New York Times |access-date=January 2, 2022 |archive-date=January 2, 2022 |archive-url=https://web.archive.org/web/20220102061109/https://www.nytimes.com/1988/06/30/us/tva-slashes-work-force-and-holds-off-on-2-plants.html |url-status=live }} In an effort to restructure and improve efficiency and financial stability, TVA began shifting towards a more corporate environment in the latter 1980s.{{cite news |last=Lippman |first=Thomas W. |date=March 29, 1992 |title=TVA: New Deal For An Old Power |url=https://www.washingtonpost.com/archive/business/1992/03/29/tva-new-deal-for-an-old-power/ca353a10-f49e-48f5-85e6-b47396aea8c1/ |newspaper=The Washington Post |access-date=March 18, 2023}} Marvin Travis Runyon, a former corporate executive in the automotive industry, became chairman of the TVA in January 1988, and pledged to stabilize the agency financially. During his four-year term he worked to reduce management layers, and reduced overhead costs by more than 30%, which required thousands of workers to be laid off and many operations transferred to private contractors. These moves resulted in cumulative savings and efficiency improvements of $1.8 billion (equivalent to ${{formatprice|{{inflation|US-GDP|1800000000|1992}}}} in {{inflation-year|US-GDP}}{{inflation-fn|US-GDP}}). His tenure also saw three of the agency's five nuclear reactors return to service,{{cite news |last=Lippman |first=Thomas W. |date=April 11, 1990 |title=For TVA, It's Back to a Nuclear Future |url=https://www.washingtonpost.com/archive/politics/1990/04/11/for-tva-its-back-to-a-nuclear-future/021659df-d094-45d8-adfa-6a3dfd925c8a/ |newspaper=The Washington Post |access-date=January 7, 2019 |archive-date=April 13, 2019 |archive-url=https://web.archive.org/web/20190413221438/https://www.washingtonpost.com/archive/politics/1990/04/11/for-tva-its-back-to-a-nuclear-future/021659df-d094-45d8-adfa-6a3dfd925c8a/ |url-status=live }}{{cite news |author= |date=August 24, 2010 |title=TVA Ala. Browns Ferry 1, 2 reactor output rises |url=https://www.reuters.com/article/utilities-operations-tva/tva-ala-browns-ferry-1-2-reactor-output-rises-idUSN2423993020100824 |work=Reuters |access-date=March 18, 2023 |archive-date=March 18, 2023 |archive-url=https://web.archive.org/web/20230318073654/https://www.reuters.com/article/utilities-operations-tva/tva-ala-browns-ferry-1-2-reactor-output-rises-idUSN2423993020100824 |url-status=live }} and the institution of a rate freeze that continued for ten years.{{cite news |title=TVA Shaped Valley Over Course of Decades New Deal Agency Tamed a River, Changed Many Lives in Impoverished Rural Areas |last=Mansfield |first=Duncan |date=July 6, 1999 |work=Birmingham News}}
= Early 1990s to late 2010s =
As the electric-utility industry moved toward restructuring and deregulation, TVA began preparing for competition. It cut operating costs by nearly $800 million a year, reduced its workforce by more than half, increased the generating capacity of its plants, and developed a plan to meet the energy needs of the Tennessee Valley through 2020.{{cite web |title=The 1990s |url=https://www.tva.com/about-tva/our-history/the-1990s |website=Tennessee Valley Authority |access-date=May 30, 2022 |archive-date=May 17, 2022 |archive-url=https://web.archive.org/web/20220517081003/https://www.tva.com/about-tva/our-history/the-1990s |url-status=live }}
In 1992 work resumed on Watts Bar Unit 1, and the reactor began operation in May 1996.{{cite news|last=Gang|first=Duane W. |date=August 29, 2014|title=5 things to know about TVA and nuclear power |work=The Tennessean|location=Nashville |url=https://www.tennessean.com/story/news/2014/08/29/tennessee-valley-authority-nuclear-power-watts-bar/14807185/ |access-date=January 7, 2019}}{{Cite web|url=https://www.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=699|title=WATTS BAR-1: Reactor Details|last=|date=|website=Power Reactor Information System|publisher=International Atomic Energy Agency|access-date=July 14, 2018|archive-date=March 13, 2017|archive-url=https://web.archive.org/web/20170313162543/https://www.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=699|url-status=live}} This was the last commercial nuclear reactor in the United States to begin operation in the 20th century.{{cite web |url=https://thebulletin.org/2015/10/watts-bar-unit-2-last-old-reactor-of-the-20th-century-a-cautionary-tale/ |title=Watts Bar Unit 2, last old reactor of the 20th century: a cautionary tale |last1=Safer |first1=Don |last2=Barczak |first2=Sara |date=October 8, 2015 |publisher=Bulletin of the Atomic Scientists |access-date=March 18, 2023 |archive-date=March 18, 2023 |archive-url=https://web.archive.org/web/20230318063951/https://thebulletin.org/2015/10/watts-bar-unit-2-last-old-reactor-of-the-20th-century-a-cautionary-tale/ |url-status=live }} In 2002, TVA began work to restart Browns Ferry Unit 1, the last of TVA's reactors that had been mothballed in 1985. This unit returned to service in 2007. In 2004, TVA implemented recommendations from the Reservoir Operations Study (ROS) on how it operates the Tennessee River system. The following year, the company announced its intention to construct an Advanced Pressurized Water Reactor at its Bellefonte site in Alabama, filing the necessary applications in November 2007. This proposal was gradually trimmed over the following years, and essentially voided by 2016.{{cite news |url=https://www.washingtonpost.com/news/morning-mix/wp/2016/09/12/for-sale-5-billion-non-working-nuclear-power-plant-as-is/ |title=For sale: Multibillion-dollar, non-working nuclear power plant, as is |author=Derek Hawkins |newspaper=Washington Post |date=12 September 2016 |access-date=12 September 2016 |archive-date=November 8, 2020 |archive-url=https://web.archive.org/web/20201108145923/https://www.washingtonpost.com/news/morning-mix/wp/2016/09/12/for-sale-5-billion-non-working-nuclear-power-plant-as-is/ |url-status=live }} In October 2007, construction resumed on Watts Bar Unit 2.{{cite web |url=http://www.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=700 |title=WATTS BAR-2 |author= |date=June 29, 2013 |website=PRIS |publisher=International Atomic Energy Agency |access-date=June 29, 2013 |archive-date=October 4, 2013 |archive-url=https://web.archive.org/web/20131004230514/http://www.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=700 |url-status=live }} which began commercial operation in October 2016. Watts Bar Unit 2 was the first new nuclear reactor to enter service in the United States in the 21st century.{{cite news |last=Blau |first=Max |work=CNN |date=October 20, 2016 |url=https://www.cnn.com/2016/10/20/us/tennessee-nuclear-power-plant/index.html |title=First new US nuclear reactor in 20 years goes live |access-date=October 20, 2016 |archive-date=October 20, 2016 |archive-url=https://web.archive.org/web/20161020193631/http://www.cnn.com/2016/10/20/us/tennessee-nuclear-power-plant/index.html |url-status=live }}
File:TVAPond.ogv, the largest environmental disaster in American history.]]
On December 22, 2008, an earthen dike impounding a coal ash pond at TVA's Kingston Fossil Plant failed, Kingston Fossil Plant coal fly ash slurry spill across {{convert|300|acre|km2}} of land and into two tributaries of the Tennessee River. The spill, of which cleanup was completed in 2015 at a cost of more than $1 billion, was the largest industrial spill in United States history, and considered one of the worst environmental disasters of all time.{{cite news |last=Bourne |first=Joel K. |date=February 19, 2019 |title=Coal's other dark side: Toxic ash that can poison water, destroy life and toxify people |url=https://www.nationalgeographic.com/environment/2019/02/coal-other-dark-side-toxic-ash |archive-url=https://web.archive.org/web/20190219140212/https://www.nationalgeographic.com/environment/2019/02/coal-other-dark-side-toxic-ash/ |url-status=dead |archive-date=February 19, 2019 |work=National Geographic |access-date=2020-05-22}} A 2009 report by engineering firm AECOM found a number of inadequate design factors of the ash pond were responsible for the spill,{{cite news |last=Barker |first=Scott |date=June 26, 2009 |title=Report: Four factors led to fly ash spill |url=http://www.knoxnews.com/news/2009/jun/26/report-four-factors-led-to-fly-ash-spill/|work=Knoxville News-Sentinel |url-status=dead |archive-url=https://web.archive.org/web/20090627180236/http://www.knoxnews.com/news/2009/jun/26/report-four-factors-led-to-fly-ash-spill/|archive-date=June 27, 2009 |df=mdy-all}} and in August 2012, TVA was found liable for the disaster by the U.S. District Court for the Eastern District of Tennessee.{{cite journal |last1=Purdom |first1=Rebecca |last2=Remmel |first2=Emily |date=May 24, 2013 |title=TVA Found Liable for Massive Coal Ash Spill But Proof of Damages Remains an Obstacle |url=http://vjel.vermontlaw.edu/topten/tva-found-liable-for-massive-coal-ash-spill-but-proof-of-damages-remains-an-obstacle/ |journal=Vermont Journal of Environmental Law |access-date=2020-05-27 |archive-date=August 3, 2020 |archive-url=https://web.archive.org/web/20200803000359/http://vjel.vermontlaw.edu/topten/tva-found-liable-for-massive-coal-ash-spill-but-proof-of-damages-remains-an-obstacle/ |url-status=dead }} The initial spill resulted in no injuries or deaths, but several of the employees of an engineering firm hired by TVA to clean up the spill developed illnesses, some of which were fatal, and in November 2018, a federal jury ruled that the contractor did not properly inform the workers about the dangers of exposure to coal ash and had failed to provide them with necessary personal protective equipment.{{cite news |last=Satterfield |first=Jamie |date=December 22, 2018 |title=On 10th anniversary of Kingston coal ash spill, workers who went 'through hell and back' honored |work=Knoxville News-Sentinel |url=https://www.knoxnews.com/story/news/crime/2018/12/22/kingston-coal-ash-spill-workers-10th-anniversary/2333826002/ |archive-url=https://web.archive.org/web/20181223183347/https://www.knoxnews.com/story/news/crime/2018/12/22/kingston-coal-ash-spill-workers-10th-anniversary/2333826002/ |archive-date=December 23, 2018 |url-status=live}}{{Cite news |url=https://www.mensjournal.com/features/coal-disaster-killing-scores-rural-americans/ |title=A Lawyer, 40 Dead Americans, and a Billion Gallons of Coal Sludge |last=Sullivan |first=J.R .|date=September 2019 |work=Men's Journal |access-date=November 2, 2019 |archive-url=https://web.archive.org/web/20191102150952/https://www.mensjournal.com/features/coal-disaster-killing-scores-rural-americans/ |archive-date=2019-11-02 |url-status=live}}
In 2009, to gain more access to sustainable, green energy, TVA signed 20-year power purchase agreements with Maryland-based CVP Renewable Energy Co. and Chicago-based Invenergy Wind LLC for electricity generated by wind farms.{{cite news |title=Dakota wind sites help TVA go green |url=https://www.timesfreepress.com/news/green/story/2009/oct/23/dakota-wind-sites-help-tva-go-green/239724/ |access-date=March 19, 2018 |work=Chattanooga Times Free Press |date=October 23, 2009 |archive-date=March 21, 2018 |archive-url=https://web.archive.org/web/20180321130339/http://www.timesfreepress.com/news/green/story/2009/oct/23/dakota-wind-sites-help-tva-go-green/239724/ |url-status=dead }} In April 2011, TVA reached an agreement with the Environmental Protection Agency (EPA), four state governments, and three environmental groups to drastically reduce pollution and carbon emissions.{{cite news |author= |title=Blockbuster Agreement Takes 18 Dirty TVA Coal-Fired Power Plant Units Offline |url=https://www.npca.org/articles/503-blockbuster-agreement-takes-18-dirty-tva-coal-fired-power-plant-units |work=National Parks Conservation Association |date=April 14, 2011 |access-date=January 7, 2019 |archive-date=January 7, 2019 |archive-url=https://web.archive.org/web/20190107232835/https://www.npca.org/articles/503-blockbuster-agreement-takes-18-dirty-tva-coal-fired-power-plant-units |url-status=live }} Under the terms of the agreement, TVA was required to retire at least 18 of its 59 coal-fired units by the end of 2018, and install scrubbers in several others or convert them to make them cleaner, at a cost of $25 billion, by 2021. As a result, TVA closed several of its coal-fired power plants in the 2010s, converting some to natural gas. These include John Sevier in 2012, Shawnee Unit 10 in 2014, Widows Creek in 2015, Colbert in 2016, Johnsonville and Paradise Units 1 and 2 in 2017, Allen in 2018, and Paradise Unit 3 in 2020.{{cite news |last=Flessner |first=Dave |date=January 8, 2018 |title=TVA cuts coal use |url=https://www.timesfreepress.com/news/business/aroundregion/story/2018/jan/06/tvcuts-coal-usejohnsville-plant-shuts-down-af/460700/ |work=Chattanooga Times Free Press |location=Chattanooga, Tennessee |access-date=January 7, 2019 |archive-date=April 4, 2019 |archive-url=https://web.archive.org/web/20190404154330/https://www.timesfreepress.com/news/business/aroundregion/story/2018/jan/06/tvcuts-coal-usejohnsville-plant-shuts-down-af/460700/ |url-status=live }}
=Recent history=
File:CRNS rendering.png, the first of several to be constructed as part of TVA's New Nuclear Program approved in early 2022.{{cite web |title=TVA Board Authorizes New Nuclear Program to Explore Innovative Technology |url=https://www.tva.com/newsroom/press-releases/tva-board-authorizes-new-nuclear-program-to-explore-innovative-technology |website=Tennessee Valley Authority |access-date=February 20, 2022 |archive-date=February 20, 2022 |archive-url=https://web.archive.org/web/20220220204744/https://www.tva.com/newsroom/press-releases/tva-board-authorizes-new-nuclear-program-to-explore-innovative-technology |url-status=live }}]]
In 2018, TVA opened a new cybersecurity center in its downtown Chattanooga Office Complex. More than 20 Information Technology specialists monitor emails, Twitter feeds and network activity for cybersecurity threats and threats to grid security. Across TVA's digital platform, two billion activities occur each day. The center is staffed 24 hours a day to spot any threats to TVA's 16,000 miles of transmission lines.{{cite news |last=Flessner |first=Dave |date=August 12, 2018 |title=Protecting the power grid: TVA beefs up security as cyber threats grow |work=Chattanooga Times Free Press |url=https://www.timesfreepress.com/news/business/aroundregion/story/2018/aug/12/protecting-power-gridgovernment-warns-russiat/476652/ |access-date=December 29, 2018 |archive-date=December 29, 2018 |archive-url=https://web.archive.org/web/20181229220523/https://www.timesfreepress.com/news/business/aroundregion/story/2018/aug/12/protecting-power-gridgovernment-warns-russiat/476652/ |url-status=live }}
Given continued economic pressure on the coal industry, the TVA board defied President Donald Trump and voted in February 2019 to close two aging coal plants, Paradise Unit 3 and Bull Run. TVA chief executive Bill Johnson said the decision was not about coal, per se, but rather "about keeping rates as low as feasible". They stated that decommissioning the two plants would reduce its carbon output by about 4.4% annually.{{cite news |url=https://www.washingtonpost.com/national/health-science/tva-defies-trump-votes-to-shut-down-two-aging-coal-fired-power-plants/2019/02/14/6cc0c9f8-3077-11e9-86ab-5d02109aeb01_story.html |title=TVA defies Trump, votes to shut down two aging coal-fired power plants |last=Mufson |first=Steven |date=February 14, 2019 |newspaper=The Washington Post |access-date=March 15, 2019 |archive-date=March 11, 2019 |archive-url=https://web.archive.org/web/20190311220523/https://www.washingtonpost.com/national/health-science/tva-defies-trump-votes-to-shut-down-two-aging-coal-fired-power-plants/2019/02/14/6cc0c9f8-3077-11e9-86ab-5d02109aeb01_story.html |url-status=live }} TVA announced in April 2021 plans to completely phase out coal power by 2035.{{cite news|last=Flessner|first=Dave|date=April 28, 2021|title=TVA plans to phase out coal power by 2035 as utility turns to more gas, nuclear and renewable energy |url=https://www.timesfreepress.com/news/business/aroundregion/story/2021/apr/28/tvplans-phase-out-coal-power-2035/545960/ |work=Chattanooga Times Free Press|access-date=2021-05-03}} The following month, the board voted to consider replacing almost all of their operating coal facilities with combined-cycle gas plants. Such plants considered for gas plant redevelopment include the Cumberland, Gallatin, Shawnee, and Kingston facilities.{{cite web |last1=Flessner |first1=Dave |title=TVA begins steps to shut down its biggest coal plant |url=https://energycentral.com/news/tva-begins-steps-shut-down-its-biggest-coal-plant.l |website=EnergyCentral |publisher=Chattanooga Times Free Press |access-date=July 4, 2021}}
In early February 2020, TVA awarded an outside company, Framatome, several multi-million-dollar contracts for work across the company's nuclear reactor fleet.{{cite web |date=February 3, 2020 |title=Framatome signs multimillion-dollar contracts with Tennessee Valley Authority |website=Framatone |url=https://www.framatome.com/EN/businessnews-1860/framatome-signs-multimilliondollar-contracts-with-tennessee-valley-authority.html |access-date=April 15, 2020 |archive-date=June 9, 2020 |archive-url=https://web.archive.org/web/20200609040446/https://www.framatome.com/EN/businessnews-1860/framatome-signs-multimilliondollar-contracts-with-tennessee-valley-authority.html |url-status=live }} This includes fuel for the Browns Ferry Nuclear Plant, fuel handling equipment upgrades across the fleet and steam generator replacements at the Watts Bar Nuclear Plant. Framatome will provide its state-of-the-art ATRIUM 11 fuel for the three boiling water reactors at Browns Ferry. This contract makes TVA the third U.S. utility to switch to the ATRIUM 11 fuel design. On August 3, 2020, President Trump fired the TVA chairman and another board member, saying they were overpaid and had outsourced 200 high-tech jobs. The move came after U.S. Tech Workers, a nonprofit that works to limit visas given to foreign technology workers, criticized the TVA for laying off its own workers and replacing them with contractors using foreign workers with H-1B visas.{{cite news |title=Trump fires Tennessee Valley Authority chair over compensation, outsourcing |work=NBC News |url=https://www.nbcnews.com/politics/white-house/trump-takes-disciplinary-action-against-tva-leadership-n1235653?cid=sm_npd_ms_fb_lw |access-date=August 4, 2020 |archive-date=October 16, 2021 |archive-url=https://web.archive.org/web/20211016204930/https://www.nbcnews.com/politics/white-house/trump-takes-disciplinary-action-against-tva-leadership-n1235653?cid=sm_npd_ms_fb_lw |url-status=live }}
Citing its aspiration to reach net-zero carbon emissions in 2050, the TVA Board voted to approve an advanced approach of nuclear energy technology with an estimated $200 million investment, known as the New Nuclear Program (NNP) in February 2022. This would promote the construction of new nuclear power facilities, particularly small modular reactors, with the first facility being constructed in partnership with Oak Ridge National Laboratory at the Clinch River Nuclear Site in Oak Ridge.{{cite web |last1=Derr |first1=Emma |title=TVA Establishes New Nuclear Program |url=https://www.nei.org/news/2022/tva-establishes-new-nuclear-program |website=Nuclear Energy Institute |access-date=February 20, 2022 |date=February 2022 |archive-date=February 20, 2022 |archive-url=https://web.archive.org/web/20220220204752/https://www.nei.org/news/2022/tva-establishes-new-nuclear-program |url-status=live }} On December 23, 2022, TVA had several hours of rolling blackouts due to the late December 2022 North American winter storm.{{Cite news |date=2022-12-23 |title=MLGW: No rolling blackouts after TVA rescinds order |url=https://wreg.com/news/local/rolling-blackouts-coming-due-to-cold-temperature/ |access-date=2022-12-23 |website=WREG-TV |archive-date=December 23, 2022 |archive-url=https://web.archive.org/web/20221223202406/https://wreg.com/news/local/rolling-blackouts-coming-due-to-cold-temperature/ |url-status=live }} As many as 24,000 Nashville Electric Service customers were without power, with thousands more from smaller distributors affected as well.{{Cite news |title=TVA ends rolling blackouts across East Tennessee |url=https://www.wjhl.com/news/regional/tennessee/tva-announces-rolling-blackouts-amid-unprecedented-demands/ |access-date=2022-12-23 |website=WJHL-TV |location=Johnson City, Tennessee |date=2022-12-23 |archive-date=February 13, 2023 |archive-url=https://web.archive.org/web/20230213095951/https://www.wjhl.com/news/regional/tennessee/tva-announces-rolling-blackouts-amid-unprecedented-demands/ |url-status=live }}{{Cite news |date=2022-12-23 |title=Outages grow in Middle Tennessee, with some without power for hours |url=https://www.newschannel5.com/news/outages-present-desperate-situation-during-dangerous-cold |access-date=2022-12-23 |work=WTVF-TV |location=Nashville |archive-date=February 13, 2023 |archive-url=https://web.archive.org/web/20230213095954/https://www.newschannel5.com/news/outages-present-desperate-situation-during-dangerous-cold |url-status=live }}
Criticism and controversies
= Allegations of federal government overreach =
TVA was heralded by New Dealers and the New Deal Coalition not only as a successful economic development program for a depressed area but also as a democratic nation-building effort overseas because of its alleged grassroots inclusiveness as articulated by director David E. Lilienthal. However, the TVA was controversial early on, as some believed its creation was an overreach by the federal government.
Supporters of TVA note that the agency's management of the Tennessee River system without appropriated federal funding saves federal taxpayers millions of dollars annually. Opponents, such as Dean Russell in The TVA Idea, in addition to condemning the project as being socialistic, argued that TVA created a "hidden loss" by preventing the creation of "factories and jobs that would have come into existence if the government had allowed the taxpayers to spend their money as they wished".{{sfn|Russell|1949|pp=10-11}} Defenders note that TVA remains overwhelmingly popular in Tennessee among conservatives and liberals alike.{{cite book |last1=Perlstein |first1=Rick |title=Before the storm: Barry Goldwater and the unmaking of the American consensus |date=2001 |publisher=Hill and Wang |location=New York |oclc=801179619 |isbn=978-0-8090-2859-7 |page=[https://archive.org/details/beforestormbarry0000perl/page/226 226] |url=https://archive.org/details/beforestormbarry0000perl/page/226}}
Business historian Thomas McCraw concludes that Roosevelt "rescued the [power] industry from its own abuses" but "he might have done this much with a great deal less agitation and ill will".{{cite book |last1=McCraw |first1=Thomas K |author-link1=Thomas K. McCraw |title=TVA and the power fight, 1933–1939 |url=https://archive.org/details/tvapowerfight00thom |url-access=registration |date=1971 |publisher=Lippincott |series=Critical periods of history |location=Philadelphia |oclc=162313 |page=[https://archive.org/details/tvapowerfight00thom/page/157 157]}} New Dealers hoped to build numerous other federal utility corporations around the country but were defeated by lobbyist and 1940 Republican presidential nominee Wendell Willkie and the conservative coalition in Congress. The valley authority model did not replace the limited-purpose water programs of the Bureau of Reclamation and the Army Corps of Engineers.
File:Ronald Reagan in General Electric Theater.jpg, who was fired by General Electric after criticizing TVA as a problem of "big government".]]
However, it has been shown that in river policy, the strength of opposing interest groups also mattered.{{cite journal |last1=O'Neill |first1=Karen M. |title=Why the TVA Remains Unique: Interest Groups and the Defeat of New Deal River Planning |journal=Rural Sociology |date=June 2002 |volume=67 |issue=2 |pages=163–182 |doi=10.1111/j.1549-0831.2002.tb00099.x |issn=0036-0112}} The TVA bill was able to attain passage because reformers like Norris skillfully coordinated action at potential choke points and weakened the already disorganized opponents among the electric power industry lobbyists. In 1936, after regrouping, opposing river lobbyists and members of congress who were part of the conservative coalition took advantage of the New Dealers' spending mood by expanding the Army Corps' flood control program. They also helped defeat further valley authorities, the most promising of the New Deal water policy reforms. When Democrats after 1945 began proclaiming the Tennessee Valley Authority as a model for countries in the developing world to follow, conservative critics charged that it was a top-heavy, centralized, technocratic venture that displaced locals and did so in insensitive ways. Thus, when the program was used as the basis for modernization programs in various parts of the third world during the Cold War, such as in the Mekong Delta in Vietnam, its failure brought a backlash of cynicism toward modernization programs that has persisted.
In 1953, President Dwight D. Eisenhower referred to the TVA as an example of "creeping socialism".{{cite news |author= |date=June 18, 1953 |title=Eisenhower Points to the T. V. A. As 'Creeping Socialism' Example |url=https://www.nytimes.com/1953/06/18/archives/eisenhower-points-to-the-t-v-a-as-creeping-socialism-example.html |page=1 |work=The New York Times |access-date=June 1, 2023 |archive-date=June 1, 2023 |archive-url=https://web.archive.org/web/20230601163122/https://www.nytimes.com/1953/06/18/archives/eisenhower-points-to-the-t-v-a-as-creeping-socialism-example.html |url-status=live }}{{cite news |last=Sturgis |first=Sue |date=April 16, 2013 |title=The strange politics of TVA privatization |url=https://www.facingsouth.org/2013/04/the-strange-politics-of-tva-privatization.html |work=Facing South |publisher=Institute for Southern Studies |location=Durham, North Carolina |access-date=June 1, 2023 |archive-date=June 1, 2023 |archive-url=https://web.archive.org/web/20230601163122/https://www.facingsouth.org/2013/04/the-strange-politics-of-tva-privatization.html |url-status=live }} The following year, then-film actor and later 40th President Ronald Reagan began hosting General Electric Theater, which was sponsored by General Electric (GE). He was fired in 1962 after publicly referring to the TVA, which was a major customer for GE turbines, as one of the problems of "big government".{{cite web |last1=Harper |first1=Liz |title=Ronald Reagan – In Memoriam: Biography |website=NewsHour with Jim Lehrer online |publisher=PBS |url=https://www.pbs.org/newshour/biography_pages/reagan/biography.html |archive-url=https://web.archive.org/web/20120227074626/https://www.pbs.org/newshour/biography_pages/reagan/biography.html |archive-date=February 27, 2012 |quote=In 1962, GE, concerned that Reagan's conservative politics made him a liability, fired him for criticizing the Tennessee Valley Authority as an example of 'big government.'}} Some claim that Reagan was instead fired due to a criminal antitrust investigation involving him and the Screen Actors Guild.{{cite news |last1=Weisberg |first1=Jacob |author-link1=Jacob Weisberg |title=The Road to Reagandom: How Reagan's eight-year gig as the host of General Electric Theater sparked his conservative conversion and became the genesis of his political career. |url=https://www.slate.com/articles/news_and_politics/politics/2016/01/ronald_reagan_s_conservative_conversion_as_spokesman_for_general_electric.2.html |access-date=March 19, 2018 |work=Slate |date=January 8, 2016 |archive-url=https://web.archive.org/web/20170718063739/http://www.slate.com/articles/news_and_politics/politics/2016/01/ronald_reagan_s_conservative_conversion_as_spokesman_for_general_electric.2.html |archive-date=July 18, 2017}} However, Reagan was only interviewed; nobody was actually charged with anything in the investigation.{{cite news |last1=Moldea |first1=Dan E. |author-link1=Dan E. Moldea |title=Ronald Reagan and his 1962 grand jury testimony |url=https://www.moldea.com/ReaganGJ.html |access-date=March 19, 2018 |newspaper=The Washington Post |date=March 15, 1987 |archive-date=February 8, 2018 |archive-url=https://web.archive.org/web/20180208010416/http://www.moldea.com/ReaganGJ.html |url-status=live }}{{cite news |agency=Associated Press |title=Inquiry Dealt With Suspected Payoffs by Conglomerate: Book Says Reagan Was Cleared in '60s Probe of MCA |url=https://www.latimes.com/archives/la-xpm-1986-09-21-mn-9247-story.html |access-date=March 19, 2018 |work=Los Angeles Times |date=September 21, 1986 |archive-date=June 30, 2016 |archive-url=https://web.archive.org/web/20160630050527/http://articles.latimes.com/1986-09-21/news/mn-9247_1_ronald-reagan |url-status=live }} In 1963, U.S. Senator and Republican presidential candidate Barry Goldwater was quoted in a Saturday Evening Post article by Stewart Alsop as saying, "You know, I think we ought to sell TVA." He had called for the sale to private companies of particular parts of the Authority, including its fertilizer production and steam-generation facilities, because "it would be better operated and would be of more benefit for more people if it were part of private industry."{{cite book |last1=Edwards |first1=Lee |author-link1=Lee Edwards |title=Goldwater: The man who made a revolution |date=1995 |publisher=Regnery |location=Washington, D.C. |isbn=978-0-89526-471-8 |oclc=624456231 |url=https://archive.org/details/goldwater00leee}} Goldwater's quotation was used against him in a TV ad by Doyle Dane Bernbach for then-President Lyndon B. Johnson's 1964 campaign, which depicted an auction taking place atop a dam and promised that Johnson would not sell TVA.{{cite book |last1=Mark |first1=David |author-link1=David Mark (journalist) |title=Going dirty: The art of negative campaigning |url=https://archive.org/details/goingdirtyartneg00mark |url-access=limited |date=2007 |publisher=Rowman & Littlefield |location=Lanham, MD |isbn=978-0-7425-9982-6 |oclc=396994651 |page=[https://archive.org/details/goingdirtyartneg00mark/page/n56 46]}}
== Legal challenges ==
The TVA has faced multiple constitutional challenges. The United States Supreme Court ruled TVA to be constitutional in Ashwander v. Tennessee Valley Authority (297 U.S. 288) in 1936.{{cite court |litigants=Ashwander v. Tennessee Valley Authority |vol=297 |reporter=U.S. |opinion=288 |year=1936 |url=https://caselaw.findlaw.com/us-supreme-court/297/288.html |archive-url=https://web.archive.org/web/20211007131042/https://caselaw.findlaw.com/us-supreme-court/297/288.html |url-status=live }} The Court noted that regulating commerce among the states includes regulation of streams and that controlling floods is required for keeping streams navigable; it also upheld the constitutionality of the TVA under the War Powers Clause, seeing its activities as a means of assuring the electric supply for the manufacture of munitions in the event of war.{{cite book |last1=Rodgers |first1=Paul |title=United States Constitutional Law: An Introduction |date=2011 |publisher=McFarland & Co. |location=Jefferson, NC |isbn=978-0-7864-6017-5 |page=48 |oclc=707092889 |url=https://books.google.com/books?id=xZ-61GFZE1kC&pg=PA48}} The argument before the court was that electricity generation was a by-product of navigation and flood control and therefore could be considered constitutional. The CEO of the Tennessee Electric Power Company (TEPCO), Jo Conn Guild, was vehemently opposed to the creation of TVA, and with the help of attorney Wendell Willkie, challenged the constitutionality of the TVA Act in federal court. The U.S. Supreme Court again upheld the TVA Act, however, in its 1939 decision Tennessee Electric Power Company v. TVA. On August 16, 1939, TEPCO was forced to sell its assets, including Hales Bar Dam, Ocoee Dams 1 and 2, Blue Ridge Dam and Great Falls Dam to TVA for $78 million (equivalent to ${{formatprice|{{inflation|US-GDP|78000000|1939}}}} in {{inflation-year|US-GDP}}{{inflation-fn|US-GDP}}).{{cite encyclopedia |last1=Ezzell |first1=Timothy |title=Guild, Jo Conn |entry=Jo Conn Guild |url=https://tennesseeencyclopedia.net/entries/jo-conn-guild/ |encyclopedia=Tennessee Encyclopedia of History and Culture |year=2009 |access-date=February 11, 2013 |archive-date=March 8, 2021 |archive-url=https://web.archive.org/web/20210308103414/https://tennesseeencyclopedia.net/entries/jo-conn-guild/ |url-status=live }}
= Discrimination =
In 1981 the TVA Board of Directors broke with previous tradition and took a hard line against white-collar unions during contract negotiations. As a result, a class action suit was filed in 1984 in U.S. District Court charging the agency with sex discrimination under Title VII of the Civil Rights Act of 1964 based on the large number of women in one of the pay grades negatively impacted by the new contract.{{cite news |title=Sex-Discrimination Action Moved Here |url=https://www.newspapers.com/article/the-knoxville-news-sentinel-sex-discrimi/124839732/ |access-date=May 17, 2023 |work=The Knoxville News-Sentinel |date=February 29, 1984 |page=B7 |archive-date=May 17, 2023 |archive-url=https://web.archive.org/web/20230517044930/https://www.newspapers.com/article/the-knoxville-news-sentinel-sex-discrimi/124839732/ |url-status=live }} TVA reached an out-of-court settlement in 1987, in which they agreed to contract modifications and paid the group $5 million (equivalent to ${{formatprice|{{inflation|US-GDP|5000000|1987}}}} in {{inflation-year|US-GDP}}{{inflation-fn|US-GDP}}), but denied wrongdoing.{{cite news |title=TVA discrimination suit settled |url=https://www.newspapers.com/article/kingsport-times-news-tva-discrimination/124839639/ |access-date=May 17, 2023 |work=Kingsport Times-News |agency=United Press International |date=March 14, 1987 |page=3A |via=Newspapers.com |archive-date=May 17, 2023 |archive-url=https://web.archive.org/web/20230517044929/https://www.newspapers.com/article/kingsport-times-news-tva-discrimination/124839639/ |url-status=live }}
= Eminent domain and resident removal =
{{multiple image
| width = 220
| image1 = View of town - NARA - 280421 cropped cleaned colorized.jpg
| alt1 = Bean Station site pre-dam
| image2 = Old Bean Station site 2021.jpg
| alt2 = Bean Station site post-dam
| direction = vertical
| footer = The historically significant town of Bean Station, Tennessee was among the largest of communities inundated by the TVA with nearly 90% of its population removed by eminent domain or federal lawsuits for the construction of Cherokee Dam.{{cite news |last1=Robinson |first1=Bonnie |title=Historic Bean Station, Oldest House in This Section, Fine Homes, and Other Landmarks Will Disappear in Cherokee Dam Lake |url=https://www.newspapers.com/image/?clipping_id=38876634 |page=26 |access-date=November 7, 2020 |work=Knoxville News Sentinel |date=April 26, 1942 |via=Newspapers.com |archive-date=December 15, 2021 |archive-url=https://web.archive.org/web/20211215175949/https://www.newspapers.com/image/?clipping_id=38876634 |url-status=live }}}}
The TVA has received criticism throughout its entire history for what some have perceived as excessive use of its authority of eminent domain and an unwillingness to compromise with landowners. All of the TVA's hydroelectric projects were made possible through the use of eminent domain,{{Cite web|title=TVA|url=https://tennesseehistory.org/tva/|access-date=July 5, 2021|website=Tennessee Historical Society|date=March 13, 2017|archive-date=July 9, 2021|archive-url=https://web.archive.org/web/20210709185348/https://tennesseehistory.org/tva/|url-status=live}} and displaced more than 125,000 Tennessee Valley residents.{{cite journal |author1=John Gaventa |title=Book Review, 'TVA and the Dispossessed: The Resettlement of Population in the Norris Dam Area' |journal=Tennessee Law Review |date=1982 |pages=979–983 |series=Symposium, the Tennessee Valley Authority |publisher=Tennessee Law Review Association |location=Knoxville, Tennessee |quote=Over the past fifty years the agency has had many opportunities to learn from its mistakes. Since 1933, over 125,000 residents have been displaced from their homesteads by TVA dam construction projects.}} Residents who initially refused to sell their land were often forced to do so via court orders and lawsuits.{{cite news |last1=McMahan |first1=Carroll |title=Douglas Dam construction created controversy, displaced families |url=https://www.themountainpress.com/news/douglas-dam-construction-created-controversy-displaced-families/article_ae65835b-2a78-571d-81d9-83810190ff82.html |access-date=August 5, 2022 |work=The Mountain Press |date=November 23, 2020 |archive-date=January 2, 2023 |archive-url=https://web.archive.org/web/20230102161624/https://www.themountainpress.com/news/douglas-dam-construction-created-controversy-displaced-families/article_ae65835b-2a78-571d-81d9-83810190ff82.html |url-status=live }}{{cite news |last=Onion |first=Rebecca |date=September 5, 2013 |title=The Tennessee Valley Authority vs. the Family That Just Wouldn't Leave |url=https://slate.com/human-interest/2013/09/tennessee-valley-authority-the-agency-s-fight-against-one-family-that-wouldn-t-sell-their-farm.html |work=Slate Magazine |access-date=March 4, 2019 |archive-date=March 6, 2019 |archive-url=https://web.archive.org/web/20190306043116/https://slate.com/human-interest/2013/09/tennessee-valley-authority-the-agency-s-fight-against-one-family-that-wouldn-t-sell-their-farm.html |url-status=live }} Many of these projects also inundated historic Native American sites and early Colonial-era settlements.Jefferson Chapman, Tellico Archaeology: 12,000 Years of Native American History (Tennessee Valley Authority, 1985).Vicki Rozema, Footsteps of the Cherokees: A Guide to the Eastern Homelands of the Cherokee Nation (Winston-Salem: John F. Blair), 135.{{Cite news |last1=Medina |first1=Eduardo |last2=Rubin |first2=April |date=2023-04-04 |title=Remains of Nearly 5,000 Native Americans Will Be Returned, U.S. Says |language=en-US |work=The New York Times |url=https://www.nytimes.com/2023/04/04/us/repatriation-native-american-remains-artifacts-tennessee.html |access-date=2023-04-05 |issn=0362-4331 |archive-date=September 24, 2023 |archive-url=https://web.archive.org/web/20230924215616/https://www.nytimes.com/2023/04/04/us/repatriation-native-american-remains-artifacts-tennessee.html |url-status=live }} Historians have claimed that the TVA forced residents to sell their property at values less than the fair market value, and indirectly destabilized the real estate market for farmland. Some displaced residents committed suicide, unable to bear the events. On some occasions, land that the TVA had acquired through eminent domain that was expected to be flooded by reservoirs was not flooded, and was instead given away to private developers.{{cite news |last=Madden |first=Tom |date=July 2, 1981 |title=Private land TVA claimed for lake to be given away to developers |url=https://www.upi.com/Archives/1981/07/02/Private-land-TVA-claimed-for-lake-to-be-given-away-to-developers/4201362894400/ |work=UPI |location=Boca Raton, Florida |access-date=March 4, 2019 |archive-date=October 25, 2021 |archive-url=https://web.archive.org/web/20211025165742/https://www.upi.com/Archives/1981/07/02/Private-land-TVA-claimed-for-lake-to-be-given-away-to-developers/4201362894400/ |url-status=live }}
= Executive compensation =
The TVA CEO Jeff Lyash’s total compensation of $10,500,000 in 2024 has generated much criticism.{{Cite web |date=2025-01-31 |title=CEO of the nation's largest public utility plans to retire |url=https://apnews.com/article/tennessee-valley-authority-tva-ceo-a243548291623ef36ca293144c5d9c5f |access-date=2025-02-01 |website=AP News |language=en}}{{cite web | url=https://nypost.com/2025/01/31/us-news/top-paid-federal-employee-leaving-10-5m-job-after-first-term-trump-said-were-getting-rid-of-him/ | title=Top-paid federal employee leaving $10.5M job — after first-term Trump said 'we're getting rid of him' | date=January 31, 2025 }}
In popular culture
The 1960 film Wild River, directed by Elia Kazan, tells the story about a family forced to relocate from their land, which has been owned by their ancestors for generations, after TVA plans to construct a dam which will flood it. While fictional, the film depicts the real-life experiences of many people forced to give up their land to TVA to make way for hydroelectric projects, and was mostly inspired by the removal of families for the Norris Dam project.{{cite news |author= |title=Wild River 50th Anniversary Celebration Plans |url=https://www.chattanoogan.com/2010/4/29/174555/Wild-River-50th-Anniversary-Celebration.aspx |work=The Chattanoogan |date=April 29, 2010 |access-date=February 3, 2019 |archive-date=February 3, 2019 |archive-url=https://web.archive.org/web/20190203202234/https://www.chattanoogan.com/2010/4/29/174555/Wild-River-50th-Anniversary-Celebration.aspx |url-status=live }}
The 1970 James Dickey novel Deliverance and its 1972 film adaptation focuses on four Atlanta businessmen taking a canoeing trip down a river that is being impounded by an electric utility, nodding to the TVA's early and controversial hydroelectric projects.{{cite web |last1=Nelson |first1=S. Tremaine |title=Deliverance Revisited: Its relevance to modern American culture is enough to give alumnus James Dickey's acclaimed novel another look |url=https://news.vanderbilt.edu/2020/10/29/deliverance-revisited-its-relevance-to-modern-american-culture-is-enough-to-give-alumnus-james-dickeys-acclaimed-novel-another-look/ |website=Vanderbilt Magazine |access-date=December 15, 2021 |archive-date=December 15, 2021 |archive-url=https://web.archive.org/web/20211215182423/https://news.vanderbilt.edu/2020/10/29/deliverance-revisited-its-relevance-to-modern-american-culture-is-enough-to-give-alumnus-james-dickeys-acclaimed-novel-another-look/ |url-status=live }} The 1984 Mark Rydell film The River focuses on an East Tennessee family being confronted by the loss of their ancestral farm from the inundation of a nearby river by an electric utility. The film, shot on farmland near the Holston River in Hawkins County, utilized flooding practical effects provided by the TVA.{{cite news |last1=Canby |first1=Vincent |title=FILM: Farmers' Plight in The River |url=https://www.nytimes.com/1984/12/19/movies/film-farmers-plight-in-the-river.html |access-date=3 April 2022 |work=The New York Times |date=December 19, 1984 |archive-date=May 24, 2015 |archive-url=https://web.archive.org/web/20150524154427/http://www.nytimes.com/1984/12/19/movies/film-farmers-plight-in-the-river.html |url-status=live }} In the 2000 film O Brother, Where Art Thou?, the family home of the protagonist, played by George Clooney, is flooded by a reservoir constructed by the TVA. This plays a central role in the pacing of the film and the broader Depression-era Mississippi context of the narrative.{{cite magazine|last=Cavanaugh|first=Tim|date=March 2001|title=O Big Brother, Where Art Thou?|url=https://reason.com/2001/03/01/o-big-brother-where-art-thou/|magazine=Reason|location=Los Angeles|publisher=Reason Foundation|access-date=July 4, 2021|archive-date=July 9, 2021|archive-url=https://web.archive.org/web/20210709183314/https://reason.com/2001/03/01/o-big-brother-where-art-thou/|url-status=live}}
"Song of the South" by country and Southern rock band Alabama features the lyrics "Papa got a job with the TVA" following the lyrics "Well momma got sick and daddy got down, The county got the farm and they moved to town" expressing the hardships and changes that southerners faced during the post recession era.{{cite web |url=https://www.wideopencountry.com/remembering-alabamas-smash-hit-song-of-the-south-watch/ |title='Song of The South': The Story Behind Alabama's Smash Hit |author= |date=July 24, 2020 |website=Wide Open Country |publisher=Publishers Clearing House |access-date=May 17, 2023 |archive-date=May 17, 2023 |archive-url=https://web.archive.org/web/20230517051117/https://www.wideopencountry.com/remembering-alabamas-smash-hit-song-of-the-south-watch/ |url-status=live }} The TVA and its impact on the region are featured in the Drive-By Truckers' songs "TVA" and "Uncle Frank". In "TVA", the singer reflects on time spent with family members and a girlfriend at Wilson Dam. In "Uncle Frank", the lyrics tell the story of an unnamed hydroelectric dam being built, and the effects on the community that would become flooded upon its completion. In 2012, Jason Isbell released a solo cover of "TVA".{{cite news |last=Opperman |first=Jeff |date=December 6, 2021 |title=Dams, Rivers And Drive-By Truckers: Songs That Explain The Challenge Of Sustainable Energy |url=https://www.forbes.com/sites/jeffopperman/2021/12/06/dams-rivers-and-drive-by-truckers-songs-that-explain-the-challenge-of-sustainable-energy/?sh=390ff61150b7 |work=Forbes |access-date=May 17, 2023 |archive-date=May 17, 2023 |archive-url=https://web.archive.org/web/20230517051533/https://www.forbes.com/sites/jeffopperman/2021/12/06/dams-rivers-and-drive-by-truckers-songs-that-explain-the-challenge-of-sustainable-energy/?sh=390ff61150b7 |url-status=live }}
See also
- Appalachian Regional Commission
- Environmental history of the United States
- Helmand and Arghandab Valley Authority, modelled on the TVA
- James Bay Energy Corporation, a Crown corporation of the Quebec government for developing the James Bay Project for building various dams on rivers
- List of navigation authorities in the United States
- Muscle Shoals Bill
- Nashville Electric Service
- New Deal
- Norris, Tennessee
- Tennessee Valley Authority Police
- Tennessee Valley Authority v. Hill
Notes
{{notelist}}
References
{{reflist}}
Bibliography
{{refbegin}}
- Barde, Robert E. "Arthur E. Morgan, First Chairman of TVA" Tennessee Historical Quarterly 30#3 (1971), pp. 299-314 [http://www.jstor.org/stable/42623246 online] {{Webarchive|url=https://web.archive.org/web/20240316174017/https://www.jstor.org/stable/42623246 |date=March 16, 2024 }}
- {{cite book |last1=Colignon |first1=Richard A. |title=Power Plays: Critical Events in the Institutionalism of the Tennessee Valley Authority |date=1997 |series=SUNY series in the sociology of work. |publisher=State University of New York Press |location=Albany, NY |isbn=978-0-585-07708-6 |oclc=42855981 }}
- {{cite book |last1=Creese |first1=Walter L. |title=TVA's public planning: The vision, the reality |date=1990 |publisher=University of Tennessee Press |location=Knoxville |isbn=978-0-87049-638-7 |oclc=476873440 |url=https://archive.org/details/tvaspublicplanni00cree |via=Internet Archive }}
- {{cite book |editor1-last=Culvahouse |editor1-first=Tim |title=The Tennessee Valley Authority: Design and persuasion |date=2007 |publisher=Princeton Architectural Press |location=New York |oclc=929309559 }}
- {{cite book |editor1-last=Hargrove |editor1-first=Erwin C. |editor2-last=Conkin |editor2-first=Paul K. |title=TVA: Fifty years of grass-roots bureaucracy |date=1983 |publisher=University of Illinois Press |location=Urbana, IL |isbn=978-0-252-01086-6 |oclc=474377514 |url=https://archive.org/details/tvafiftyyearsofg00harg |via=Internet Archive }}
- {{cite book |last1=Hargrove |first1=Erwin C. |title=Prisoners of myth: the leadership of the Tennessee Valley Authority, 1933–1990 |date=1994 |publisher=Princeton Univ. Press |location=Princeton, NJ |series=Princeton Studies in American Politics: Historical, International, and Comparative Perspectives |isbn=978-0-691-03467-6 |jstor=j.ctt7rvbh |url=https://archive.org/details/prisonersofmythl00harg |via=Internet Archive }}
- {{cite journal |last1=Kull |first1=Donald C. |title=Decentralized Budget Administration in the Tennessee Valley Authority |journal=Public Administration Review |date=Winter 1949 |volume=9 |issue=1 |pages=30–35 |doi=10.2307/972660 |issn=0033-3352 |oclc=5544417850 |jstor=972660}}
- {{cite book |last1=Lilienthal |first1=David E. |author-link=David E. Lilienthal |title=TVA: Democracy on the march |url=https://archive.org/details/tvademocracyonma0000lili |url-access=registration |date=1953 |publisher=Harper & Row |location=New York |via=Internet Archive }}
- {{cite book |last1=Morgan |first1=Arthur E. |author-link1=Arthur Ernest Morgan |title=The making of the TVA |url=https://archive.org/details/makingoftva0000morg |url-access=registration |date=1974 |publisher=Prometheus Books |location=Buffalo, New York |isbn=978-0-87975-034-3 |oclc=607606121 |via=Internet Archive }}
- {{cite book |last=Neuse |first=Steven M. |date=1996 |title=David E. Lilienthal: The Journey of an American Liberal |location=Knoxville, Tennessee |publisher=The University of Tennessee Press |isbn=0-87049-940-8 |url=https://books.google.com/books?id=6I-pDwAAQBAJ |via=Google Books |access-date=March 22, 2023 |archive-date=June 24, 2023 |archive-url=https://web.archive.org/web/20230624061324/https://books.google.com/books?id=6I-pDwAAQBAJ |url-status=live }}
- {{cite book |last=Neuse |first=Steven M. |date=2004 |editor-last=McElvaine |editor-first=Robert S. |chapter=Tennessee Valley Authority (TVA) |title=Encyclopedia of Great Depression |location=Farmington Hills, Michigan |publisher=Macmillan Reference USA |url=}}
- {{cite journal |last1=Neuse |first1=Steven M. |title=TVA at Age Fifty—Reflections and Retrospect |journal=Public Administration Review |date=November–December 1983 |volume=43 |issue=6 |pages=491–499 |doi=10.2307/975916 |issn=0033-3352 |oclc=5550047671 |jstor=975916}}
- {{cite book |last1=Neuse |first1=Steven M. |title=David E. Lilienthal: the journey of an American liberal |date=1996 |publisher=University of Tennessee Press |location=Knoxville |isbn=978-0-87049-940-1 |oclc=243857932 }}
- {{cite book |last1=Russell |first1=Dean |title=The TVA idea |date=1949 |publisher=Foundation for Economic Education |location=Irvington-on-Hudson, New York |oclc=564022 |url=https://books.google.com/books?id=eH5BAAAAIAAJ |via=Google Books |access-date=March 19, 2023 |archive-date=June 24, 2023 |archive-url=https://web.archive.org/web/20230624061324/https://books.google.com/books?id=eH5BAAAAIAAJ |url-status=live }}
- {{cite book |last=Talbert |first=Roy Jr. |date=1987 |title=FDR's Utopian: Arthur Morgan of the TVA |location=Jackson, Mississippi |publisher=University Press of Mississippi |isbn=0-87805-301-8 |url=https://books.google.com/books?id=6I-pDwAAQBAJ |via=Google Books |access-date=March 22, 2023 |archive-date=June 24, 2023 |archive-url=https://web.archive.org/web/20230624061324/https://books.google.com/books?id=6I-pDwAAQBAJ |url-status=live }}
- {{cite book |last1=Wilson |first1=Marshall A. |title=Tales From the Grass Roots of TVA, 1933-1952 |date=1982 |publisher=Wilson Publishing |location=Knoxville, Tennessee |oclc=1011650240 }}
{{refend}}
External links
{{Commons and category|Tennessee Valley Authority|Tennessee Valley Authority}}
- {{Official website|www.tva.com}}
- [https://www.federalregister.gov/agencies/tennessee-valley-authority Tennessee Valley Authority] in the Federal Register
- {{cite wikisource |title=Procedure for Making, Indexing and Filing Computations |author=Tennessee Valley Authority |date=March 1950}}
- [https://digital.lib.utk.edu/collections/wpa-tva WPA Photographs of TVA Archaeological Projects]
- {{YouTube|eoge1KmeMy8|The New Deal and TVA}}
- [http://eisenhower.archives.gov/Research/Finding_Aids/J.html Papers of Arnold R. Jones (Member of the Board of Directors, Tennessee Valley Authority), Dwight D. Eisenhower Presidential Library]
- [https://www.tva.com/about-tva/our-history TVA history]
- {{Internet Archive short film|id=gov.fdr.353.3.3|name=Valley of the Tennessee {{noitalic|(1944)}}}}
{{Tennessee Valley Authority Facilities}}
{{New Deal}}
{{Authority control}}
Category:1933 establishments in Tennessee
Category:1933 establishments in the United States
Category:73rd United States Congress
Category:American companies established in 1933
Category:Appalachian Mountains
Category:Companies based in Knoxville, Tennessee
Category:Corporations chartered by the United States Congress
Category:Economic development organizations in the United States
Category:Electric power companies of the United States
Category:Energy companies established in 1933
Category:Energy companies of the United States
Category:Energy infrastructure in Tennessee
Category:Government agencies established in 1933
Category:Hydroelectric power companies of the United States
Category:Independent agencies of the United States government
Category:New Deal in Tennessee
Category:Nuclear power companies of the United States
Category:Public utilities of the United States
Category:United States Department of Energy
Category:Water management authorities in the United States